Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...

Page created by Vincent Stewart
 
CONTINUE READING
Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...
Scheme: Superfast Broadband
               Full Business Case Monitoring & Evaluation Plan
1. Scheme background and context
 Provide a short description of the scheme, including costs, the delivery timeframe and an explanation of the
  wider delivery context.
 A summary of the key milestones should be provided with expected and actual completion dates.
(indicative 250 words)

Broadband Delivery UK (BDUK), part of the Department for Culture, Media and Sport, is delivering superfast
broadband across the country to areas where there are no commercial plans over the coming three years.

The Government is providing grant funding to local authorities which has to be matched £1 for £1 to:
     provide superfast broadband coverage to 90% of the UK by early 2016 and 95% by December 2017
     provide access to universal access to basic broadband (2Mbps) for all from December 2015
     explore options to provide superfast coverage to the hardest to reach parts of the UK

South Gloucestershire Council’s (SGC)Superfast Extension Programme (SEP) is being delivered over in 3 Phases:
    Phase 1 to increase superfast coverage from 82% to 90% from 2013 to 2015.
           o £2,710,000m was invested with BT using BDUK framework contract in March 2013.
           o The investment consisted of £710,000 BDUK funding; £2,000,000m SGC funding;
           o Deployed completed March 2015, under budget, exceeding contractual target.
           o Delivering fibre broadband to 17,965 business and residential premises.
    Phase 2 to increase superfast coverage from 90% to 93%; during 2015 to 2017.
           o £1,010,000m is being invested with BT using BDUK framework contract which signed in March
               2015.
           o The investment consist of £510,000 BDUK and£500,000 SGC.
           o Deployment due to completed March 2017.
           o Deliver fibre broadband to 2,899 premises
    Under their Phase 2, SGC has an option to apply additional funding through its Phase 2 SEP.
           o A Contract Change request has raised to invest a further £1.49m through Phase 2.
           o The investment consist of £306,000 underspend from Phase 1 contract; £601,000 clawback
               from our Phase 1 contract and £381,000 of WoE LGF funding.
           o Deliver fibre broadband to 1825 premises
           o This will further increase superfast coverage 93% to 95%
    Phase 3 aspiration is to increase superfast coverage from 95% to 98%/99% through and OJEU
       Procurement for £3,000,000m during 2017 to 2018.
           o The investment consist of £1,500,00m BDUK South West fund; £650,000 BDUK; £929,000 WoE
               LGF;
         a) Following an Open Market review and public consultation, we have 5281, white premises in our
            intervention area and a further 5230 premises currently under review in the NGA Intervention
            Area and are not to be targeted area for Phase3.
         b) Further details on the deployment will be provided once a preferred supplier has been select and
            contract are signed

This M&E Plan has been completed for SGC Phase 2 SEP and additional investment and will be further updated
with information relating to Phase 3 once procurement has been completed.

                                                                                                          1
     Doc v.1 Last updated May 2016
     Submission date: 05/01/2017        Submitted by: Nita Patel           Approved: 06/01/2017
Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...
Scheme: Superfast Broadband
2. Logic Model
 Complete a logic model to reflect the project scope i.e. all the activities covered by the investment. Ensure also
  that there is a clear progression between the steps in your logic model.
 State assumptions between the investment and the predicted outcomes and impacts.
 For outcomes relating to direct jobs creation, please provide an annual profile of jobs created and clearly state
  the time period over which net additional jobs and GVA will be created.
 Please define the impact area of the intervention ie West of England or other geographical scale.
(indicative 350 words)

                                                                                                             2
     Doc v.1 Last updated May 2016
     Submission date: 05/01/2017         Submitted by: Nita Patel            Approved: 06/01/2017
Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...
Scheme: Superfast Broadband
       Logic Model

Context and Rationale
Provide a brief description of the strategic and policy context (link to local and national strategy policy). Briefly describe the market failure rationale for the intervention.

Stimulating investment in the UK‟s broadband infrastructure is a top priority. The Broadband Delivery Programme covers the delivery of the Government’s investment and policy approach to bring forward network infrastructure upgrades and to improve the
accessibility of services in locations where there is a weak commercial investment case. Broadband Delivery UK (BDUK) has been created within the Department for Culture, Media and Sport (DCMS) to be the delivery vehicle for the government‟s policies
relating to stimulating private sector investment using the available funding.

Objective                                     Resources/ Input                               Activities                                     Outputs                                      Direct & Indirect Outcomes                     Impact
The aims/ objectives of the scheme are:       In order to achieve the set of activities to   In order to address the aims and objectives    We expect that, once accomplished these      We expect that if accomplished these           We expect that if accomplished these
(Ensure that all aims/objectives are          fulfil these aims/ objectives we need the      we will accomplish the following activities:   activities will produce the following        outputs will lead to the following change      activities will lead to the following changes
SMART)                                        following:                                     (What will the money be used for? e.g.         deliverables:                                e.g. new products or services, skills,         in service, organisation or community:
                                              (Resources should not be limited to money      construction, project management,              (Provide measurable outputs e.g. length of   behaviour, new business/contracts, etc:        (quantitative economic impacts e.g.
                                                                                                                                                                      2
                                              e.g. grant, match funding, in-kind, project    equipment/fit out, etc):                       new road/cycle path, m of space              (Ensure that all outcomes are SMART and        indirect jobs and/or GVA to be cross-
                                              team, specialist support, etc. The inputs                                                     constructed/refurbished, number of           relevant to the aims/objectives to allow for   referenced with FBC as appropriate)
                                              define the scope of the project being                                                         businesses supported, learners engaged,      attribution; distinguish between direct and
                                              considered in the logic model )                                                               etc)                                         indirect outcomes)
 Phase 2 – Superfast Extension               LGF capital funding - £1,310m over             SGC Project management and                   o This Phase will use “fibre to the           Jobs connected to Programme                   Investment on site - Target spend
  Programme (SEP) - deliver faster             2016/17 and 2017/18.                            support                                        cabinet” (FTTC) technology.                  Management & Support - 1.5 Direct              £1,01m by Q4 2016/17
  fibre connectivity to those areas             o For this Phase £0.500m LGF                  Planning and survey of existing/new          o 50 cabinets will be upgrade in South         FTE                                           Net additional GVA during
  where there is or will not be any               funding will be spend over                   ducting, cabinet or copper rewiring            Gloucestershire by Q3 2016/17.              Direct jobs connected to the                   operational phase - An increase in
  commercial offering over the next               2016/17                                      work.                                        o Total length of fibre installed will be      implementation phase and contract              South Gloucestershire’s GVA of an
  three years (2014 – 2017)                     o Leaving £0.810m to spend                    Civils work to install/upgrade                 confirmed at the end of the                  duration. – 3PTE                               average 2.1% p.a. between 2010
 Fibre broadband will be delivered to            through the remaining Phases.                existing/new ducting, cabinet or               programme (please note that it’s not                                                        and 2030.
  a total of 2,899 premises;                                                                   copper rewiring                                possible to estimate the length fibre
  o 1842 will be delivered by Q2              Match funding from BDUK & SCG -                                                                to be installed until full planning and
      2016/17                                  £3,757m over 2016/17, 2017/18 and                                                              survey work has been completed).
  o 1057 will be delivered by Q4               2018/19.                                                                                     o Fibre will be delivered to a total of
      2016/17                                   o For this Phase £0.510m will be                                                              2,899 premises of which 1,690 will
  o 1690 will be superfast (24 mpbs               spend over 2016/17                                                                          be superfast (24 mbps or more)
      or more)                                  o Leaving £3,457m

                                              SGC Programme team includes::
                                                 o Adhoc Independent telecoms
                                                    consultancy
                                                 o Full Project Officer to manage
                                                    day-to-day operational
                                                    management of supplier
                                                 o Programme Manager
                                                 o Finance Support to manage
                                                    financial payment.
                                                 o Legal support to advice on FOI
                                                    requests and any contractual
                                                    issues or change request.

                                              SGC Programme team includes:
                                                 o State Aid compliance
                                                    assurance
                                                 o Value for Money assurance
                                                                                                                                                                                                                                                                            3
       Doc v.1 Last updated May 2016
       Submission date: 05/01/2017           Submitted by: Nita Patel               Approved: 06/01/2017
Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...
Scheme: Superfast Broadband
                                            o   Commercial and legal team
                                                assurance and approve
                                                contract change
                                            o   Project Director single point of
                                                contact into BDUK

 Phase 2 SEP - Addition Investment       LGF capital funding - £1,310m over                             South Gloucestershire:                   Same as above for Phase 2 SEP    Investment on site - Target spend
  deliver faster fibre connectivity to     2016/17 and 2017/18.                                            o Deployment will be through                                                £1.37m by Q3 2017/18
  those areas where there is or will not    o For this Phase £0.381m LGF                                       “fibre to the cabinet” (FTTC) and                                      Net additional GVA during
  be any commercial offering                  funding will be spend over                                       “Fibre to the Premise” (FTTP)                                           operational phase - An increase in
 Fibre broadband will be delivered to        2016/17                                                          technology by Q3 2017/18.                                               South Gloucestershire’s GVA of an
  a total of 1825 premises by Q3            o Leaving £0.429m to spend                                     o Length of fibre will be confirmed                                         average 2.1% p.a. between 2010
  2017/18.                                    through the OEJU.                                                at the end of each quarter.                                             and 2030.
  o Phase 2a - 255 premises will be                                                                            (please note that it’s not
     delivered by Q3 2017/18.             Match funding from BDUK & SCG -                                     possible to estimate the length
  o Phase 2b - 594 premises will be        £3,757m over 2016/17, 2017/18 and                                   fibre to be installed until full
     delivered by                          2018/19.                                                            planning and survey work has
  o Phase 2c - 976 premises will be         o For this Phase £1.107m will be                                   been completed)
     delivered                                spend over 2016/17                                           o 1678 premises will be superfast
  o 1678 premises will be superfast         o Leaving £3,079m to spend                                       (24 mpbs or more)
     (24 mpbs or more)                        through OJEU

                                        SGC Programme team includes::
                                           o Adhoc Independent telecoms
                                              consultancy
                                           o Full Project Officer to manage
                                              day-to-day operational
                                              management of supplier
                                           o Programme Manager
                                           o Finance Support to manage
                                              financial payment.
                                           o Legal support to advice on FOI
                                              requests and any contractual
                                              issues or change request.

                                        SGC Programme team includes:
                                           o State Aid compliance
                                              assurance
                                           o Value for Money assurance
                                           o Commercial and legal team
                                              assurance and approve
                                              contract change
                                           o Project Director single point of
                                              contact into BDUK

                                                                                                                                                                                                                   4
      Doc v.1 Last updated May 2016
      Submission date: 05/01/2017      Submitted by: Nita Patel           Approved: 06/01/2017
Scheme: Superfast Broadband Full Business Case Monitoring & Evaluation Plan - The West of England ...
Scheme: Superfast Broadband
 Phase 3 - OJEU procurement for        LGF capital funding - £1,310m over                            The following information will be            Follow on investment at site –
  £3m                                    2016/17 and 2017/18.                                          provided once a preferred supplier has         target spend and timescales?
 Our aspiration is to achieve 98%/99%    o For this Phase £0.429m of                                  been identified and contract signed.           Source?
  fibre coverage across South               remaining LGF funding will be
  Gloucestershire.                          spend over 2016/17 and                                        Specific locations? By when?
 Following an Open Market review           2017/18                                                       Type and length of fibre cabling?
  and public consultation, we have                                                                        Broadband speed delivered?
  5281, white premises in our           Match funding from BDUK & SCG -                                  Other outputs?
  intervention area.                     £3,757m over 2016/17, 2017/18 and                                Increase in ultrafast broadband
 A further 5230 premises currently      2018/19.                                                          coverage from XX% to XX% in the
  under review in the NGA                 o For this Phase £2,650m will be                                 intervention area by 20XX
  Intervention Area and are not to be       spend over 2016/17 and
  targeted area for Phase 3. However,       2017/18.
  these may considered at a later date
                                        Our evaluation criteria will weight
                                         business premises and ultrafast
                                         speed high when evaluating bidders
                                         response for the OJEU

                                        SW Ultrafast Broadband £1.5m

                                                                                                                                                                                  5
      Doc v.1 Last updated May 2016
      Submission date: 05/01/2017      Submitted by: Nita Patel         Approved: 06/01/2017
Scheme: Superfast Broadband
3. Evaluation design and methodologies
 Describe your key evaluation questions e.g what do you want to find out?
 Referring back to the outcomes and impacts stated in the logic model (section 2), describe your evaluation
  methodology (ie. process, outcome or impact, or a combination).
 Identify your audiences and evaluation stakeholders, and what their evaluation needs may be.
 Are the scheme beneficiaries easily identifiable and accessible?
(indicative 300 words)

      Our key evaluation questions are on economic benefits including GVA.
      Our requirement will be defined based on ‘value for money’ (vfm) to deliver the most coverage for the
       available funding which has and will continued to be assured by SGC and BDUK within Central governance
       DCMS. Detailed methodology as agreed with BDUK is attached. The process will take into account extent of
       delivery to time, cost, budget and scope; alignment of deployment with the contractual implementation
       plan; lessons learned (including effectiveness of delivery via partnership working).
      outcomes - ‘value for money’; coverage and broadband speed against targets; provision of
       superfast/ultrafast broadband in rural areas
      The scheme beneficiaries will the business and residents of South Gloucestershire which will be captured
       through contractual C3 Report which provides Customer Take-up and Access Requests on the
       monthly/quarterly basis.

4. Data requirements
4.1 For schemes fully or part-funded via the Local Growth Fund only
 Relevant performance indicators will be provided for each scheme when a draft logic model is shared at, or
    prior to, submission of a Full Business Case for approval.

    Metric                Unit             Frequency             Data source        Baseline   Reporting to?
    (inc. Target)                                                (&                 date
                                                                 Responsibilit
                                                                 y)
    Inputs
    Funding breakdown     £1,310m LGF      Quarterly             Contracts          31/03/15   LEP highlight
    £5,577m               £1,607m SGC                            deliverables                  report
                          £2,660m BDUK
                                                                 Grant Offer                   BDUK MPC
                                                                 letter                        Assurance Check
                                                                 agreements
                                                                 with funding                  Milestone
                                                                 bodies                        Achievement
                                                                                               report
                                                                 Programme                     (MAR/MER)
                                                                 Manager

    Outputs
    Phase 2                                                      Detailed                      Project
    Cabinets Installed    55 cabinets      Quarterly             design plans –                governance, Yr1
    EO/CuRE upgrade                                              Main                          evaluation report
                                                                 contractor

    Fibre installed       Km of Fibre      Quarterly
                                                                                                               6
        Doc v.1 Last updated May 2016
        Submission date: 05/01/2017        Submitted by: Nita Patel               Approved: 06/01/2017
Scheme: Superfast Broadband

 Phase 2                1842 will be    Quarterly /          Contractual C3     15/16       LEP highlight
 Fibre broadband        delivered by    Annually             reports and                    report, BDUK,
 will be delivered to   Q2 2016/17                           monthly take-                  Quarterly
 a total of 2,899                                            up reports                     Assurance review
 premises;              1057 will be                                                        Project Closure
                        delivered by                                                        Assurance review
                        Q4 2016/17

                        1690 will be
                        superfast (24
                        mpbs or
                        more)

 Outcomes and impacts
 Jobs connected to  1.5 FTEs            Duration of the      1.5 Direct FTE     03/2015 –   LEP highlight
 Programme                              Programmes                              09/2018     report;
 Management &
 Support
 Direct jobs        3 PTE               Project Lead &       3 PTE:                         Tracked through
 connected to the                       Network              Project Lead       03/2015     quarter milestone
 implementation                         Deployment           Network            03/2017     pay claim
 phase and contract                     Manager for                                         assurance.
 duration.                              Implementation       Deployment         03/2015
                                        Period               Manager            03/2022

                                        Finance Lead for     Finance Lead       03/2015
                                        contract duration.                      03/2017

 Net additional GVA     £               **An increase in     Ex-ante            03/2019     Project
 during operational                     South                economic                       governance, Yr 3
 phase                                  Gloucestershire’s    appraisal –                    evaluation report
                                        GVA of an            Project
 *An increase in                        average 2.1% p.a.    Manager
 broadband speeds                       between 2010
 will help businesses                   and 2030.
 increase
 productivity

* This will be in a number of ways, but the greatest immediate impact may be through the increased
opportunities for flexible working. The technologies and applications made possible such as cloud computing,
will mean employees can access hardware or software from any location using an internet connection.
Videoconferencing will mean that employees can attend meetings without spending time and money travelling
to the meeting location. Flexible working patterns are already most common in the financial and professional
services sector. This is also the sector where the opportunities from SFB are likely to be greatest.

                                                                                                            7
     Doc v.1 Last updated May 2016
     Submission date: 05/01/2017        Submitted by: Nita Patel              Approved: 06/01/2017
Scheme: Superfast Broadband
** The primary strategic benefit of the investment that will be made through this project is through an increase
in South Gloucestershire’s GVA. South Gloucestershire’s Local Economic Assessment 2011 forecasts potential
local economic growth (measured by Gross Value Added, GVA) of an average 2.1% p.a. between 2010 and
2030. This would see South Gloucestershire’s GVA increase from £6,090,000 in 2010 to £10,542,000 in 2030.

4.2 Data collection methods
 Provide an overview of the data collection approaches including timing and frequency of data collection.
 Describe links with other monitoring activities where relevant.
 Where appropriate, provide maps showing the spatial coverage of the data collection.
(indicative 250 words)

The approach to data collection is to utilise existing and ongoing quarterly Milestone to Cash (M2C) process
and reporting as on the attached.

  M2C Process and
reporting manual V1.0 [1].pdf

4.3 Data collection and establishing the baseline
 Refer to thone scheme logic model to help structure the baseline data collection and reporting activities.

Baseline data collection and reporting activities are as defined within our BDUK National Framework contract
for Phase 2 SEP and Additional investment change request. An overview of the data collection approach
including timing and frequency of the data collection and establishing the baseline, its links with relevant
monitoring activities as detailed on the attached Milestone to Cash (M2C) Process and reporting manual and
Milestone to Cash Process maps which are/will be assured and reviewed with BDUK and SGC Programme
Board.

  M2C Process and          Milestones to cash
reporting manual V1.0 [1].pdf process.pdf

5. Delivery plan
 Provide a project plan and timeframe for data collection and reporting of monitoring and evaluation findings
  (ie. when key activities will take place, including baseline work, interim and final findings).
(indicative 250 words)

As stated in Section 4.2 and 4.3, the sources of data to be used are collected quarterly

The baseline year for Phase 2 SEP and additional investment is 2015 with the following phased
deliverables as follows:

 Phase         Sub-phase            THP Int M2
 Phase         Phase 1a             921
                                            2016 - 2017 Q2
 1             Phase 1b             921

                                                                                                           8
      Doc v.1 Last updated May 2016
      Submission date: 05/01/2017               Submitted by: Nita Patel    Approved: 06/01/2017
Scheme: Superfast Broadband
            Phase 1c         1057
                                        2016 - 2017 Q4
            Phase 1d         0
            Phase 2a         255
 Phase
            Phase 2b         594        2017-2018 Q3
 2
            Phase 2c         976
            Grand Total      4,724

Quarterly assurance reports as details in section 4.2 Milestone to Cash process will be provided to
SGC Finance Officer, BDUK and LEP Accountable body.

Programme closure assurance report will be provided to SCG Finance Officer, BDUK and LEP but will
not be fully published due non-disclosure contract clauses

Annual take-up reports will be provided to SGC Finance Officer, BDUK and LEP Accountable body.

6. Resourcing and Governance
 Provide details of the monitoring and evaluation budget, including details of source and what costs/activities
  this will pay for.
 Clarify procedures for risk management and any quality checking.
 Describe opportunities for different stakeholders to input into the scheme evaluation process.
 Provide a named contact responsible for delivering the plan, including name, address, telephone and email.
(indicative 250 words)

Cost for monitoring and evaluation budget will be covered as part of the Business as Usual (BAU) programme
operational management through the attached Milestone to Cash (M2C) Process and reporting manual
detailed in sections 4.2 and 4.3 to ensure contractual deliverables in terms of FTTC, FTTP, THP, and speed
bucket are achieved.

By utilising existing and ongoing operational contract management, the primary resource requirement will be
officer time to collate, analyse, review and report which will be completed using the BAU Milestone to Cash
(M2C) Process and reporting detailed in sections 4.2 and 4.3 to ensure contractual deliverables in terms of
FTTC, FTTP, THP, and speed bucket are achieved.
Responsibility for monitoring and evaluation sits with a nominated officer in South Glos Council, who reports to
the programme manager. The programme manager monitors and manages risk. The programme manager
reports to a Senior Responsible Officer.
The Senior Responsible Officer reports South Gloucestershire Council Chief Executive.

The Programme Board reports to the Resources Sub committee, Senior Responsible Officer within South
Gloucestershire Council, Senior Responsible.

The named contact responsible for delivering the plan is Nita Patel, South Gloucestershire Council, Department
for Environment and Community Services, PO Box 299, BRISTOL, BS15 0DR. Telephone: 01454 862085. Email:
Nita.Patel@southglos.gov.uk

7. Dissemination

                                                                                                           9
     Doc v.1 Last updated May 2016
     Submission date: 05/01/2017        Submitted by: Nita Patel           Approved: 06/01/2017
Scheme: Superfast Broadband
 Provide details of how the findings from the evaluation will be used. What will the evaluation inform and who
  will be the audience?
 Please provide details of how the findings from the evaluation will be communicated to key stakeholders and
  lessons disseminated.
(indicative 250 words)

The finding from the evaluation form part of the assurance process which is reviewed by SGC Programme
Board and BDUK to ensure contract terms and deliverables have been met, state aid and vfm achieved. The
finding from the quarterly reviews are documented and reviewed with SGC Programme Board and BDUK teams
where lessons learnt are shared across all BDUK projects.

The evaluation will be shared with partners, interested stakeholders, staff within each delivery authority as
well as the funding body to ensure that the impact and outcome of the funding can be demonstrated to future
decision makers. The evaluation will also present case studies for any future similar interventions in the region.

                                                                                                          10
     Doc v.1 Last updated May 2016
     Submission date: 05/01/2017         Submitted by: Nita Patel           Approved: 06/01/2017
DCMS – Broadband Delivery UK

     Milestone to Cash (M2C)
     process and reporting
     Manual
     V1.0 10th July 2014

     COMMERCIAL AND IN CONFIDENCE

M2C Reports and process manual Jul 14.doc
Contents
Introduction............................................................................................................................................. 5
   Use of this document .......................................................................................................................... 5
   Approval .............................................................................................................................................. 5
   Template Versions covered by this document .................................................................................... 5
Description of reports ............................................................................................................................. 6
   Milestone Achievement Report (MAR) Evidence Template ............................................................... 6
   Spine(or Spider) Diagram(s) ................................................................................................................ 6
   Speed at M0 Report ............................................................................................................................ 6
   C3 (Services Availability Tab) ............................................................................................................... 6
   THP Tracker ......................................................................................................................................... 7
   Milestone Payment Claim (MPC) Template ........................................................................................ 7
   Finance Tracker ................................................................................................................................... 7
Who will receive these reports and when?............................................................................................. 7
Why do BDUK receive this data? ............................................................................................................. 9
   Cross Border Assurance....................................................................................................................... 9
   VFM reports......................................................................................................................................... 9
   C3 analysis ........................................................................................................................................... 9
   Infrastructure deep dive...................................................................................................................... 9
Reporting Template Descriptions.......................................................................................................... 10
MAR Evidence Template (MS Excel)...................................................................................................... 10
       Version Control.............................................................................................................................. 10
       Baseline Tab (MAR Evidence Template) ........................................................................................ 10
       Postcode Tab (MAR Evidence Template) ...................................................................................... 10
       Head-ends Tab (MAR Evidence Template) .................................................................................... 11
       Spines Tab (MAR Evidence Template) ........................................................................................... 11
       FTTC Tab (MAR Evidence Template) ............................................................................................. 12
       FTTP Tab (MAR Evidence Template) ............................................................................................. 13
       FTTx (Delta) Tab (MAR Evidence Template) .................................................................................. 13
       Cross Border .................................................................................................................................. 13
       Note. Colour Coding ..................................................................................................................... 13
   Spine Diagrams .................................................................................................................................. 14
M0 Speed Report................................................................................................................................... 16
   The Quarterly Customer Report – The C3 report .............................................................................. 17

2|Page
Who receives the C3 report?......................................................................................................... 17
       Why is the C3 report important? .................................................................................................. 17
       What’s different about the very first C3 report? .......................................................................... 17
       The New Product availability tab .................................................................................................. 17
       How does the C3 report align to the THP tracker? ....................................................................... 18
       Central assurance of the C3 report ............................................................................................... 18
       Central assurance steps................................................................................................................. 18
       Has the THP IP target been met .................................................................................................... 18
       Has the THP IA target for the SCT been achieved ......................................................................... 18
       Is the deficit as calculated by BT adequate? ................................................................................. 19
       Has the THP been delivered in the right speed buckets? ............................................................. 19
       Any other noted data issues.......................................................................................................... 19
       Limitations to central assurance ................................................................................................... 19
THP Tracker ........................................................................................................................................... 20
       Intro tab ......................................................................................................................................... 20
       THP Baseline Data ......................................................................................................................... 20
       Implementation THP ..................................................................................................................... 21
Milestone Payment Claim (MPC) .......................................................................................................... 23
       Version and Legal notice tabs ....................................................................................................... 23
       Milestone Payment Request ......................................................................................................... 23
       M0, M1 & M2 Transactions ........................................................................................................... 23
       Adjustments to Prior claims .......................................................................................................... 23
       Estimates not closed ..................................................................................................................... 24
       Direct Labour back up ................................................................................................................... 24
       Planning Job type .......................................................................................................................... 24
       Estimates not in MAR evidence..................................................................................................... 24
       Tracker Mapping ........................................................................................................................... 24
Finance Tracker ..................................................................................................................................... 25
   Finance tracker tab............................................................................................................................ 25
       Fixed contract values ..................................................................................................................... 25
       Source of funding .......................................................................................................................... 25
       Total actual qualifying capital incurred ......................................................................................... 25
       Qualifying capital linked to milestone payment claims/WIP ........................................................ 25
Frequently Asked Questions ................................................................................................................. 27

3|Page
What is an estimate? ......................................................................................................................... 27
   What is the MAR Evidence Template? .............................................................................................. 27
   Where are spine estimates shown in the MAR? ............................................................................... 27
   How is an MPC raised? And how does it relate to the MAR Evidence Template ............................. 27
   What about unclosed estimates?...................................................................................................... 28
   What information can a Local Body request in relation to information appearing on a MAR
   Evidence Template or Milestone Payment Claim? ........................................................................... 28
   What type of Headends will be used within the programme? ......................................................... 29
Appendix A - M2C Information Flow ..................................................................................................... 30
Appendix B - Milestone to Cash Templates populated with dummy data ........................................... 31

4|Page
Introduction

Use of this document
BDUK, BT and representatives of some Local Bodies have been working together to agree a revised
M2C reporting set that provides Local Bodies with sufficient evidence to prove and assure the
achievement of each milestone along with the qualifying capital expenditure items that support the
Milestone payment claims. These enhanced, and in some cases new reports, will be provided on a
quarterly basis to all Local Bodies on the Framework and to some Local Bodies not on the
Framework, that are adopting the M2C Process. They:

    •        satisfy the supporting evidence to be provided by BT to prove Achievement of each
             milestone type as defined in Appendix A of Schedule 4.1 of the Call Off Contract
    •        largely satisfy the quarterly reporting requirements under the Grant Agreement
    •        satisfy the reporting requirements as defined in Schedule 6.4 of the Call Off Contract,
             specifically C1, C3 and C61.
    •        satisfy the reporting requirements under the Framework Agreement between BDUK and
             BT as defined in Schedule 8, specifically F2, F3, F4 and F5.

This document is intended for use by Local Bodies to understand the enhancements made to existing
reports and to additional back up reporting provided by BT from July 2014.

Approval
This document contains content produced by both BDUK and BT and has been approved for release
by both organisations.

Template Versions covered by this document
This manual covers the following versions of the reporting templates in question

       MAR Evidence Template               Version 3.1
       Spine Diagram                       Version N/A (Local to each Local Body)
       M0 Speed Report                     Version 1.0
       C3 (Services Availability Tab)      Version 4.5
       THP Tracker                         Version 1.0
       MPC Template                        Version 2.0
       Finance Tracker                     Version 3.0

Should a Local Body receive a different version of any of these templates after 1st July, they should
refer in the first instance to their BT Group contact and seek a replacement based on the most
current version as described above.

1
 The MAR Evidence Template does not in itself fulfil the requirements of a C2 report as set out in Schedule 6.4,
which requires a monthly update. This will need to be resolved at a local level, though we note that a monthly
refresh of the MAR would meet the requirement.

5|Page
Description of reports

See Annex B for Huddle links to these templates supplemented with dummy data and with
row/column descriptions.

Milestone Achievement Report (MAR) Evidence Template
The MAR evidence template details the activity undertaken by BT in order to plan and build the
structures needed to fulfil the contract. At both the M0 and M1 milestone, it will be the primary
document by which BT provide the evidence needed to prove achievement of the milestone to allow
the Local Body to issue a Milestone Acceptance Certificate. At the M2 milestone, it will be used with
the THP tracker (which includes data sourced from the C3 report) to prove milestone achievement.
The MAR is an incremental tracker report and at the end of the deployment will provide a record of
the infrastructure delivered. It satisfies the reporting requirements as defined in C1 of Schedule 6.4
of the Call off Contract.

Spine(or Spider) Diagram(s)
This document will provide visual depiction of the infrastructure planned, delivered, and/or used
(commercially, deployed) from exchange (head-end), via fibre spines (including spine lengths) and
aggregation nodes through to DSLAMS and cabinets (PCPs). Infrastructure will be labelled/coded
enabling cross-check to the MAR evidence template. The diagrams will also show commercially built
infrastructure where Local Body assets have been appended to existing BT infrastructure. Where
spine lengths cross borders, these will also be delineated on the diagrams. These diagrams are live
operational documents used by BT through the planning and deployment stages. Issues affecting the
build (such as blockages and de-silting) will also be identified.

Speed at M0 Report
This new report will be provided at each M0 showing all the structures planned to be built for a given
phase. It will include post code to structure mapping along with predicted modelled speeds by
postcode from the Chief Engineers Model (CEM). The speed buckets are 0-15, 15-24 & 24+ Mbs. Each
month the report will be reissued with the customer ready service (CFRS) date included for all the
cabinets that have gone live in the prior month and on a cumulative basis. BDUK recommend that
the report be used as supporting evidence to prove achievement of the M0 as defined in Schedule
4.1 Appendix A i.e “per premise estimated Access Line Speeds for Wholesale Access Products and
Services actoss the scope of this Milestone”. This report will be completed using THP
(Implementation Plan) premises so will be different to the THP(Intervention Area) speeds reported at
each M2.

C3 (Services Availability Tab)
This document will report the Total Homes Passed within the Implementation Plan THP(IP) passed by
BT in the last quarter, providing per premise predicted upspeed and downspeed line speed for all
structures that have been made Commercially Ready for Service (CRFS) for a given M2. It will be the
key input into the THP Tracker, the document that BT will submit to prove achievement of an M2. It
also satisfies the part of the C3 report of Schedule 6.4 of the Call Off Contract that requires a “report
that identifies “Retail Ready” wholesale access products and services and availability (by

6|Page
town/village, postcode, street and house ID)”. The other C3 reporting requirements as specified in
Schedule 6.4 are yet to be agreed with BT.

THP Tracker
BT is contractually required to achieve the THP deployment targets as set out in both the
Implementation Plan and the Speed and Coverage Template (SCT) targets, at the specified Access
Line Speed ranges per Phase as set out in the SCT. The THP tracker displays these contracted baseline
volumes, taken from the contract Schedules 4.1 (Implementation) normally in Appendix 2 for
Framework contracts) and Schedule 3.1 where the SCT is held. and also demonstrates BT’s actual
performance against them.

The THP Tracker Baseline Tab calculates the deficit between the two target THP numbers, both by
Phase and in Total for the delivery proposed. The THP IP numbers delivered by Baseline Structure
provides the THP deficit baseline from which achievement is measured.

The THP Tracker Implementation THP tab, shows the THP (IP) achievement within the against which
the deficit value is applied to evidence achievement against SCT. The Implementation Plan tab also
has the input for the speed categories (buckets) to measure these against the SCT targets

Milestone Payment Claim (MPC) Template
The MPC template will contain details of the expenditure incurred by BT to achieve the milestone
along with the contractual Milestone Payment being claimed. It will be the primary document by
which the Local Body can assure that the expenditure incurred is permitted capital expenditure. It
will provide an overview of the total qualifying capital incurred and then allocate this cost against
the milestones claimed in the period. It will also provide a detailed picture of the costs claimed at an
estimate level broken down by the milestone they relate to as well as the category of cost providing
a link back to the both the network planned/delivered to achieve the relevant milestone, along with
a link to further supporting evidence (invoices, receipts) should it be required. This detailed picture
also allows linkage, in most cases, to individual infrastructure delivered.

Finance Tracker
The finance tracker is the key document used to track the financial performance of the contract. It is
comprised of four sections describing

    1. Fixed contracted values ( from the PFM, and contract [Sections 4.1 & 3.1]),
    2. Source of funding (BT, public subsidy),
    3. Total actual qualifying capital incurred (broken down into the same cost categories as the
       project financial model)
    4. Total qualifying capital linked to claim milestone payment claims ( claimed, claimed & paid
       and WIP).

Who will receive these reports and when?
The M2C Information Flow diagram V2.0 at Annex A describes when templates will be received and
by whom.

7|Page
As described in Appendix A of Schedule 4.1 of the Call Off Contract BT will provide; MAR evidence
template, Spine Diagram, C3 and THP Tracker to the Local Body, no later than 20 working days after
the relevant Milestone Date. The Milestone Payment Claim and accompanying transaction listing will
be issued within 5 working days of BT receiving the Milestone Acceptance Certificate from the Local
Body. As part of the agreements between BDUK and BT, BDUK will receive copies of Local Bodies
MAR evidence C3 report and THP tracker. BDUK receive these reports only when the Local Body has
completed their initial assurance and issued a MAC. BDUK will also receive copies of Finance Tracker
and MPC once Local Body assurance is complete.

These reports will largely satisfy the reporting requirements as defined in Schedule 5 of the Grant
Agreement 1) Build and Roll-Out Report and 2) Customer report (bullet 1 only). BDUK will not
routinely receive the M0 Speed Report or spine diagrams from BT, although BDUK may request
occasional samples of these templates in order to carry out routine assurance.

8|Page
Why do BDUK receive this data?

Cross Border Assurance
BDUK will be able to use the evidence provided in the MAR evidence templates to conduct detailed
assurance on BT’s approach to cross-border structures, ensuring that cross-border structures are
correctly and consistently noted in the MAR evidence template for neighbouring Local Bodies. It will
remain the responsibility of the Local Body who will be paying for the relevant structure to assure the
associated actual qualifying capital expenditure.

VFM reports
By analysing the data from the MPCs, Finance Tracker,THP Tracker, and MAR evidence documents,
BDUK will produce actual cost comparison reports, showing Local Bodies’ costs versus the original
bid and against other LB’s. BDUK will issue these reports to all Local Bodies who have achieved a
milestone in Q1 14/15. This report is intended to enable Local Bodies and BDUK to assess at a high
level if value for money is being achieved as referenced against the Reference Financial Model,
against the bid and as compared to each other.

C3 analysis
BDUK will carry out central assurance on C3 reports to assure that THP IP reporting accurately
reports on THP IP volumes achieved, and that the application of a calculated deficit (as evidenced in
the THP tracker) continues to produce a correct view of SCT achievement.

BDUK analysis carried out on 100% of C3 reports (and accompanying THP Trackers) for M2’s achieved
in Q4 13/14. Both the IP Prems passed (per the C3 reports) and the White premises passed (as
compared to the SCT) were deemed to be an accurate and correct reflection of the achievement.

From Quarter 1, 50% of all M2s will be randomly assessed and the results will be shared with the
relevant Local Body.

Infrastructure deep dive
These documents will assist BDUK as part of its routine deep dive investigations of BT costs. BDUK
will analyse particular parts of LB’s build to assess the cost of delivery. This will be used along with an
independent audit review for Central Government assurance of the Programme.

9|Page
Reporting Template Descriptions
The section below includes details of agreed enhancements in the M2C reporting suite which will
largely be implemented from Q1 14/15. In some cases, BT has not completed all the development to
automate certain elements of the reports. Those limitations, which will be rectified from Q2 14/15
are documented and a forward looking view given of what’s coming in subsequent milestones.

MAR Evidence Template (MS Excel)
The Q1 2014 version (3.0) of the MAR template is an Excel Spreadsheet with nine tabs. The first two
are a version control tab plus an overview tab and these are consistent for all contracts. The
remaining seven tabs have data specific to each Local Body’s network, consisting of Baseline,
Postcode, Head-End, Spine, FTTC, FTTP and FTTx (Delta). The Head-end, Spine, FTTC and FTTP tabs
include colour coding so that the Local Body can see which activities are associated with M0 (yellow
columns), M1 (light blue columns) and M2 (purple columns). In addition, each column has a
definition where appropriate which is identified by the red link in the corner of the cell.

Data is populated directly from BT systems with the exception of the ‘Commercial’ column (is a Head-
end/Spine part of BT’s commercial deployment?) and ‘Cross Border’ (is the structure shared with
another Local Body and which is responsible for financing it?) both of which are manually populated

The MAR evidence template will have some significant developments between July and September
2014, in readiness for the Q2 milestones. The template has been set for July milestones so that the
report doesn’t need to change structure in the next quarter.

Version Control
This shows the version of the template and any changes made from the previous version.

Baseline Tab (MAR Evidence Template)
This tab shows a list of all Head-ends and Structures that have primarily been identified by the CEM
with allowed adjustments for a Local Bodies Priority areas or ERDF requirements. These
Infrastructure elements form basis for the network that BT plans to deploy to achieve the contractual
speed and coverage that is proposed and documented in Schedule 4.1 Appendix 2 of the Call Off
contract ( or equivalent for Non Framework contracts). The phasing of each deployment is found on
the Head-end, Spine and FTTC tabs. Any changes to these baseline structures will be posted to the
FTTC delta tab. The Phases in which the FTTX structures were to be deployed to deliver the SCT will
be identified along with the exchange area, PCP reference number, current PCP location and PCP
Easting and Northing.

BT state that this list of PCPs are included as an illustration of the network BT plan to deploy to
achieve contractual SCT. However the timing and specific nature of the structure deployed is not
contractually binding and can be changed at BT’s discretion, as long as BT maintain the stated
coverage area i.e. the postcodes , premises passed and speed targets as per the SCT.

Postcode Tab (MAR Evidence Template)
This contains the complete list of postcodes served by each structure. It is a listed format view so
each structure may appear several times depending on the number of postcodes it serves.

10 | P a g e
Head-ends Tab (MAR Evidence Template)
This is the equipment in the Telephone Exchange on which the fibre network terminates.

Estimate numbers for the activities that have been used to deploy the Head-end in M1 can be viewed
by using the ‘+’ sign above column BA.

Spines Tab (MAR Evidence Template)
Spines are identified by unique optical network (ON) numbers.

The route of the spine can be plotted using the Starting T Code and Agg Node in Columns F and G.

Node to Node length is in Column H

 In Q1 MAR’s, aggregation nodes linked to a starting T code will appear, separated by commas in
this column.

From Q2 (end of September), each aggregation node will appear sequentially on a separate line.
Similarly, Agg node length will not appear until Q2. Both pieces of information are available from
the spine diagrams.

Build estimate numbers, shown below, are included for the spine at M0 in this spreadsheet. These
build estimates will also appear in the FTTC tab at M1, along with other spine related to connect the
structure to the nearest aggregation node.

                                              M0
                                                     M0 Change
     M0 Complete   Build Estimate   Finalise Fibre
                                                      Control      M0 MAR Reference
         Date           No(s)       Spine Design
                                                     Reference
      30/06/2013   IBFH0FMG            17/06/2013                Phase 1 M0 2013-14 Q1
      30/06/2013   IBFH1EMH            17/06/2013                Phase 1 M0 2013-14 Q1
      30/09/2013   IBFD6RJH            29/08/2013                Phase 2 M0 2013-14 Q2
      30/09/2013   IBFD6RJH            29/08/2013                Phase 2 M0 2013-14 Q2
      30/09/2013   IBFD6RJH            29/08/2013                Phase 2 M0 2013-14 Q2

11 | P a g e
FTTC Tab (MAR Evidence Template)
Each Primary Connection Point (PCP) or cabinet has a separate row with its reference number listed
in Column D.

The Spine and Agg Node references are in Columns J and K and can be cross checked with the Spine
Diagrams

At M1, all the activities listed in Columns AI to AO are associated with the deployment of the fibre
infrastructure (Spine/Blown Fibre Tubing/Desilting etc) by which the cabinet is served.
                                                                                                                                                                                                                                          Spine Cabling (or Spine
                                                                                                                      Fibre Tail Jointing (or
   M1            Light Loss M1 Change                                       BFT (Tubing)                                                      FPC Joint Working Gully Sucking/De-                  Measure Light      OCR Cabling and      Cabling & Jointingor
                                                                                                BFT Civils Estimate     Copper Ties, Fibre
Complete        end to end   Control          M1 MAR Reference                Estimate                                                             Estimate      Silting Estimate                  Loss Estimate     Jointing Estimate       Spine Subduct &
                                                                                                    Number(s)             Tail Jointing)
  Date           test date  Reference                                        Number(s)                                                           Number(s)          Number(s)                       Number(s)           Number(s)            Cabling) Estimate
                                                                                                                      Estimate Number(s)
                                                                                                                                                                                                                                                Number(s)
30/09/2013       18/09/2013                 Phase 1 M1 2013-14 Q2        IBFMWVNN, IBG81CRV                           IBFNRLTL                                                                                       IBFL86CV            IBFH1EMH
30/09/2013       26/09/2013                 Phase 1 M1 2013-14 Q2        IBFMWEKY                                     IBFMWKNP                                                                                       IBFL86CV            IBFH0FMG
30/09/2013       24/09/2013                 Phase 1 M1 2013-14 Q2        IBFN90WK                                     IBFND2EH                                                                                       IBFL86CV            IBFH2FKL
31/03/2014       21/01/2014                 Phase 1 M1 2013-14 Q4        IBFP6GMH        IBGFWDPJ                     IBFPC8AX, IBH09UTH                                                                             IBFL86CV            IBFH1EMH
31/12/2013       17/12/2013                 Phase 1 M1 2013-14 Q3        IBFP6GMH        IBGFWDPJ                     IBFPECWL                                                                                       IBFL86CV            IBFH1EMH
30/09/2013       16/09/2013                 Phase 1 M1 2013-14 Q2        IBFMW3FU                                     IBFMWDHT                                                                                       IBFL86CV            IBFH1VVE
30/09/2013       16/09/2013                 Phase 1 M1 2013-14 Q2        IBFMWVNN                                     IBFNCTEN                                                                                       IBFL86CV            IBFH1EMH
31/12/2013       12/11/2013                 Phase 1 M1 2013-14 Q3        IBFMWVNN        IBGCFKLT                     IBFND6PD                                                                                       IBFL86CV            IBFH1EMH, IBFWC2WU
30/09/2013       24/09/2013                 Phase 1 M1 2013-14 Q2        IBFN90WK                                     IBFNDKUP                                                                                       IBFL86CV            IBFH2FKL
30/09/2013       24/09/2013                 Phase 1 M1 2013-14 Q2        IBFMWVNN                                     IBFNCEKM                                                                                       IBFL86CV            IBFH1EMH
30/09/2013       24/09/2013                 Phase 1 M1 2013-14 Q2        IBFN90WK                                     IBFNE5JY                                                                                       IBFL86CV            IBFH2FKL

As cabinets will be sharing spines, many of the Build Estimate numbers are the same. These columns
are hidden in the spreadsheet and revealed using the ‘+’ in Column AP.

At M2, deployment activities are generally exclusive to that cabinet so the Build Estimate numbers
are unique. These columns are revealed by using the ‘+’ in Column BR.

There will be many more build estimate numbers for FTTC compared to the Spine. Each of the
estimate numbers can be either unique to that cabinet if the work relates only to that structure (i.e.
all build estimates in M2), or can be split between cabinets where their build is shared (i.e. some
build estimates in M1 for spine/head end).
                                                                                                                                         Copper Ties &
                                                                                                                                                             Deload Reload
   M2                                             Openreach M2 Change                             Copper Civils   Copper Test Rod     Jointing (or Copper                       Deload Reload     DSLAM Electrical   DSLAM I&C     DSLAM Order    DSLAM Telemetry
             Structure T- Structure C- Implement                                                                                                               Cabling and
Complete                                          Marketable Control      M2 MAR Reference          Estimate         Estimate            Ties, Fibre Tail                       Civils Estimate   Meter Estimate      Estimate       Estimate         Estimate
                 RFS          RFS       ation THP                                                                                                           Jointing Estimate
  Date                                             Premises Reference                              Number(s)        Number(s)          Jointing) Estimate                         Number(s)         Number(s)        Number(s)      Number(s)        Number(s)
                                                                                                                                                               Number(s)
                                                                                                                                           Number(s)
31/12/2013    21/10/2013   29/10/2013       397        316              Phase 1 M2 2013-14 Q3                                       IBFLHTHS, IBFVCWCV                                            IBFJ4ERS                                        IBFJ47NX
31/12/2013    25/11/2013   02/12/2013       490        451              Phase 1 M2 2013-14 Q3                                       IBFLJ8JE                                                      IBFJ5KAP                                        IBFJ5EDE
31/12/2013    11/11/2013   18/11/2013       358        303              Phase 1 M2 2013-14 Q3                                       IBFLJFCM                                                      IBFJ7WKH                                        IBFJ7TUM
31/03/2014    13/02/2014   25/02/2014       376        360              Phase 1 M2 2013-14 Q4                                       IBFLJRJW                                                      IBFJ8JMK                                        IBFJ8GKB
31/12/2013    14/12/2013   19/12/2013       256        254              Phase 1 M2 2013-14 Q3                                       IBFLK2KW                                                      IBFJG8GF                                        IBFJG5UP
30/09/2013    27/09/2013   03/10/2013       238        192              Phase 1 M2 2013-14 Q2                                       IBFLKDAJ                                                      IBFTJGHC                                        IBFTJEMD
30/09/2013    23/09/2013   02/10/2013       357        310              Phase 1 M2 2013-14 Q2                                       IBFLKJNL                                                      IBFJK1RR                                        IBFJJRVY
31/12/2013    25/11/2013   02/12/2013       867        813              Phase 1 M2 2013-14 Q3                                       IBFLKWPS                                                      IBFK5RJU                                        IBFK5JCU
30/09/2013    23/09/2013   02/10/2013       553        509              Phase 1 M2 2013-14 Q2                                       IBFLLHWV                                                      IBFK7FKA                                        IBFK70NW
30/09/2013    23/09/2013   02/10/2013       564        466              Phase 1 M2 2013-14 Q2                                       IBFLLNUF                                                      IBFK8DDS                                        IBFK87VY
31/12/2013    11/11/2013   18/11/2013       421        405              Phase 1 M2 2013-14 Q3                                       IBFLM2PH                                                      IBFK8UHH                                        IBFK8NFR

12 | P a g e
FTTP Tab (MAR Evidence Template)
The information provided in this tab is similar to the FTTC tab. There are different activities
associated with the deployment of FTTP and these are reflected in the Build Estimates within the
hidden columns.

FTTx (Delta) Tab (MAR Evidence Template)
As the project progresses, there will be changes to the baseline that will need to be recorded. The
removal from the build area or addition from the no-build area of FTTC/FTTP structures is recorded
in this tab, though a Local Body should note that this will normally require a change control.

The movement of structures between phases should also be recorded on this tab.

Cross Border
The Head-end, Spine, FTTC and FTTP tabs each have columns at the right of the spreadsheet which
identifies whether the structure is affected by the Cross Border policy. For example, the route of the
spine may cross a county border resulting in structures being located in a different county.

If these columns are empty, then there is no cross border issue with the structure. BT will complete
these columns if the Head-end, Spine and/or structure is affected by the Cross Border policy.

To ensure that these templates are correctly interpreted, and that additional information is available
to Local Bodies, BT will be providing spine diagrams, which will illustrate where there is cross border
structure deployed. BDUK will conduct central assurance that these cross border columns are being
correctly populated.

Note. Colour Coding
The MAR evidence template is colour coded as follows;

Columns with no Shading will be completed for all structures before the first M0 (apart from Cross
Border which is completed at the M0 stage)

Columns Shaded Yellow will be completed at the relevant M0 for the structure

Columns Shaded Green will be completed at the relevant M1 for the structure

Columns Shaded Purple will be completed at the relevant M2 for the structure

13 | P a g e
Spine Diagrams
                                Spine diagrams are operational documents used internally within BT to manage and monitor the
                                infrastructure roll out. They detail the build status of each head end, spine and cabinet. They are
                                annotated to show where there are issues/problems in the build (i.e. duct blockages) and where
                                spines/cabinets have been completed.

                                These diagrams are updated regularly and can be shared with Local Bodies to help support and
                                interpret the MAR evidence template and to fill in the gaps at Quarter 1 14/15 where automated
                                reporting of the MAR is delayed. They will be available on a quarterly basis to support the MAR
                                evidence template. They may also be made available to Local Bodies on a monthly (or more
                                frequently than quarterly) basis, if required and through local agreement, to support regular
                                governance meetings with SPMs. Any ad hoc requests for Spine Diagrams should be made locally
                                and provided where operationally possible.

                                The following is a fictitious example of a spine diagram. It identifies the Head End, Spine (using ON
                                Number), Agg Node (using ‘T’ code) and cabinet. It will show stoppages, commercial spines (where
                                appropriate), identify fibre distances and county borders.

                                BT spine diagrams may vary nationally. They will, however be consistent within an LB.

                                                                                                                                                                                                                          1   Cab Removed / Deferred
                       OM: Quentin Cumber
oppage
                       Allocator: Noah Lott                                                                                                                                                                               1   Cab Requires Replan
ew Duct                OMA: Hugh Eversleft
                       Co-ord: Constance Noring                                           Spendlebury (SC) Spine ON10824/10822/10821/46168                                                                                1   Cab Not Stood
esilt / Jet
                       Lead Eng: Hazel Knutt                                                                                                                                                                              1   Cab Stood
unday Working /                                                                                To Yanksnorton
affic Management
                                                       ON10824                                                                                                                                                            1   Cab with Power
oppage Complete
(Not yet Cabled)                                   COF 200-96F                                                                                                                                                            1   Cab with Meter Cert
ew Duct Complete                                       923m/1014.95m
 (Not yet Cabled)                   SC                                    ZDBZN                                                                                                                                           1   Cab with 212 Check
                                                                                                              15                                                                                                              Completed but
esilt / Jet Complete                                       A
                                                                                                                                                                                                                          1   NO NI Work Done.
 (Not yet Cabled)
                                                                                 a/0m            b/25m
                                                                                                                                                                          3                                       a/1m    1   Cab with Copper
 t Built                                                   ON10821
                                                                                COF 200-96F                                                                                                         11                    1   Cab Powered with Copper
Place –                                                          A
nting In Progress                                                                     472m/519.2m                  COF 200-96F                                    b/36m
                                                ON10822                                                                                                                                    d/168m                         1   Cab with M/C & Copper
Jointing Complete                                                                                                 401m/441.1m
                                                                                                  ZDBZL                                  ZDBZK                                                                            1   Cab with Fibre
                                                                  COF 200-48F                                             B                                                    c/499m                    e/8m
ble Route                                                  A
                                                                      901m/990.64m                         a/0m                                                                                                           1   Cab with Power & Fibre
                            A                                                                                                                        a/0m                                                        14
                                                                                                                         b/65m           10
 Duct Complete                         597m/656.7m                                                                                                                                                                        1   Cab with M/C & Fibre
                                                                                                                                                            18
                                                                                  ZDBZJ                                          f/211m                                                                                   1   Cab with NI Complete
                           ON46168
OF Complete
                                                                                                                                                      g/4m                             5
                                                                                        a/0m                                                                          i/4m                                                1   Cab with Power & NI Comp
Route

                                                                                                                                  c/99m              h/177m
                                                                                                                                                                                                                          1   Cab with M/C & NI Comp
                                                                Greens Norton                     b/407m             6
 BFZ Complete                                                                                                                                                                 j/494m
                                                                                                             35
                                                                                                                                                                                                                          1   Cab Complete (Job Pack)
 BFB Complete                                 COF 200-96F              ZDBZM                                                                      e/153m
                                                                                                          c/1795m                                                                 9
                                             2140m/2353.87m                                                                                                                                                                           Exchange with OC
 oint for SPINE                                                                                                               d/334m                                                                                      NAME
                                                                                                                                                             13                                                                     Cable Chamber Inco
                                                                                 a/0m                                4
 oint for ZR&Z                                             B
                                                                                                                                                                                                                                       Exchange with O
                                                                                                    2                                                                                                                     NAME
m (276F)                                                                                                                            12                                                                                               (inc Hydra’s) Comp
 & Fibre Size
                                                                                                                                                                                                                      8
                                             ZBEDB/A                   b/487m           c/9m                                                                                                             b/15m
                                                                                                                                                                                                                                          Exchange wit
rence Number
                                                                                                                                                                                                                          NAME       Cable Chamber Com
                                                                                                                                                                                             a/1m
                                                          COF 200-24F             7                                                                                                                                                    Exchange with O
     JUF 6                                                                                                                                                                                                                NAME       Cable Chamber Co
s 123 Made Up Rd                                               10m/11m
    B12 3AB                                                                                     ZBEDB                                                                                      ZBEDE
                                                                  C                                                                           D                                                                                               PCP Requir
  NODE box type
                          Existing Network                                                                          COF 200-24F                        2800m/3080m                                                                          PCP with Re
    & Address                                                                                                                                                                                                                             (Deleted when

                                14 | P a g e
You can also read