RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst

Page created by Cecil Acosta
 
CONTINUE READING
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
RF 2020-2021 Outreach Approach,
Lessons Learned, Best Practices & Cold
         Weather SAR Update
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
RF 2020 Cold Weather Readiness Approach due to COVID-19
  As in the past, targeted entities (new generating facilities) and existing facilities that experienced
   first-time cold weather-related issues, would be requested to complete the RF Plant Winterization
   Survey. The deadline for these submittals would be extended due to COVID-19.

  As in the past, targeted entities for existing generating facilities that experienced repeat cold
   weather-related issues, would be requested to update their previous responses to the RF Plant
   Winterization Survey. The deadline for these submittals would also be extended due to COVID-19.

  Onsite site visits would be conducted if permitted by the generating facility or RF per each
   organization’s COVID-19 guidelines.

  In lieu of site visits, off-site spot checks would be conducted utilizing RFI’s and WebEx discussions
   in coordination with the plant staff commitments and availability due to COVID-19 .

  In lieu of site walk downs to confirm readiness of potential problem areas or mitigation of previous
   cold weather-related issues, photos would be requested. Videos would also be considered.

 2                                        Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
RF Evaluation of GADS Data
 After evaluation of GADS data based on cold weather-related issues, only four generating facilities
  met the RF 500 MW threshold to be considered for a winter readiness activity.

 Since the amount of MWHs lost were minimal in all cases including the duration of these derates, it
  was determined that no form of follow-up was required at this time.

 RF attributed a reduction in the number of facilities and MWHs impacted by cold weather due to a
  mild winter which resulted in the following:
    • Lower peaks/average loads
    • No major winter emergency events
    • Few emergency procedures were required
    • No gas pipelines issues were encountered
    • Minimal generation alerts were issued
    • Improved generator performance due to established cold weather preparation practices

 Also, there were no new generating facilities registered in RF during 2020.

3                                         Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
2020-2021 Winter Forecast (NOAA/Farmer’s Almanac)
 It is predicted that recent warming trends will dominate in the eastern and northern parts of the U.S. for the upcoming winter,
  with below-normal average temperatures limited to the western portion of the nation. The winter will not be extremely cold;
  instead, it will be closer to normal.

 On the precipitation side of things, expect “wet” to be a wintertime constant, with rain or average to below-average snowfall to
  be the standard throughout most of the country. Specifically, precipitation will be below normal from Delaware into North
  Carolina and the southern Appalachians. Snowfall will be greater than normal in the Northeast, Wisconsin, Upper Michigan,
4 and the High Plains; with below normal snowfall in most other areas that receive snow.
                                                  Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
RF Winter Readiness Recommendations (GO/GOP)
 Begin winter readiness preparations in October to allow ample time to correct any deficiencies.

 Be aware of your facility’s minimum ambient design or winter operating temperature.

 Consider MISO or PJM winter guidelines as required or deemed appropriate.

 Ensure any lessons learned have been included in winter readiness program especially those they
  may impact the generation fleet or those with similar configurations.

 Complete training of operations and maintenance staff so they understand their roles and
  responsibilities regarding winter readiness.

 Ensure that MISO or PJM are always made aware of any cold weather-related operating limitation
  and the standby status of the generating facility (prewarming mode, maintaining flow through critical
  piping systems/equipment, idle and full, or drained).

 Ensure that all cold weather-related data is provided to MISO or PJM prior to a cold weather event.

5                                      Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
ERCOT/TRE Weatherization Workshop

    2019-2020:
       80 units spot checked (November to February)
       Fuel types
         • Three coal-fired units
         • 71 gas-fired units (conventional and combined cycle)
         • 6 gas-fired black start contracted units.
       23 units agreed to improve preparations and/or records
        management
       57 units had no observed deficiencies

6                         Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
ERCOT/TRE Weatherization Workshop

    Common freezing causes of transmitter manifolds
    and/or sensing lines:
      • Tripped heat trace circuit breaker
      • Blown fuse in heat trace panel
      • Contractor error when terminating heat trace after testing
      • Insulating contractor damage to heat trace
      • Section of heat trace not functioning
      • Incorrect heat trace for application
      • Heat trace open-ended and not grounded
      • Transmitter cabinet heater not functioning
      • Poor or lack of wind break measures
      • Transmitter(s) exposed to elements
      • Gaps in insulation

7                            Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
ERCOT/TRE Weatherization Workshop
    Lesson Learned No. 1 - November 12, 2019
       • During cold front, a CT experienced a trip due to transition steam flow showing a
         high reading.
       • Inspection of the transmitter box showed that the heater and heat trace were not
         energized.
            ‒ I&C technician found that the RTD (resistance temperature detector) that measures
              ambient temperature to energize the heat trace circuits had failed. Manufacturer
              default for a RTD failure was to de-energize heat trace circuits.
            ‒ It was also discovered that the transmitter box thermometer was reading 15 degrees
              higher than actual enclosure temperature which caused the operator conducting the
              rounds to record a false reading.
       •   Corrective actions:
            − RTDs were replaced on all heat trace panels of this type.
            − These heat trace panels were re-programed to energize heat trace circuits upon
              failure.
            − All transmitter box enclosure thermometers were replaced.
            − During 2020 spring outage, internal box temperatures were telemetered to GMS for all
              critical transmitters for monitoring by control room operators.
            − Lesson learned was shared with remainder of company fleet.

8                                     Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
ERCOT/TRE Weatherization Workshop
    Heat trace panel – resistance temperature detector (RTD) failure

9                              Forward Together • ReliabilityFirst
RF 2020-2021 Outreach Approach, Lessons Learned, Best Practices & Cold Weather SAR Update - ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Lesson Learned No.2:
        ‒ Winter readiness plan was in place, but vague in many areas.
             • Success of the plan was highly dependent on prior knowledge of the
               plant.
             • Many critical areas of the facility were not explicitly part of the plan
               such as instrument air systems and heat trace circuits.
        ‒ Winter readiness plan was revised to include:
             • Critical heat trace testing and comparison to previous year
             • Critical insulation inspection
             • Instrument air system readiness testing to ensure adequate dryness
             • Minimum staffing requirements for the different phases of the winter weather plan
             • Specified the different tasks required for winter preparation for each craft
             • Developed a list of the critical areas in the plant that needed to be addressed
               based on experience

10                                Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.1:
        ‒ Due to freezing issues on the air-operated controller for the Feedwater
          Control Valve, a removable insulation blanket was first utilized before
          fabricating a temporary metal enclosure around the control valve assembly.

        ‒ Also to eliminate the possibility of condensation in the instrument air system,
          certain PMs associated with the air dryers such as filter replacement,
          desiccant replacement and dew point monitor calibration were implemented.

11                             Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.2 – Enhancement of Heat Trace Circuit
       Tracking:

12                        Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.2 – Enhancement of Heat Trace Circuit
       Tracking:

13                        Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.2 – Enhancement of Heat Trace Circuit
       Tracking:

14                        Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.2 – Enhancement of Heat Trace Circuit
       Tracking:

15                        Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.3 – Inclusion of iMonnit system as a remote
       method of monitoring the transmitter boxes.
        ‒ Benefits of Remote Temperature Monitoring:
            • Global vs Individual Alarming
                  DCS will alarm a Heat Trace Panel; however, this includes several circuits
                   with several transmitter boxes.
                  iMonnit allows individual box alarms.
                       Allows O&M staff to troubleshoot quickly
                       Temperature sensor alarms allow for prompt maintenance before it becomes a
                        bigger issue
            • Ability to trend temperature data
            • Quick dashboard view of the heat trace health
            • Additional personnel are not needed for physical box rounds during
              cold weather
                  Physical rounds of transmitter boxes every 2-4 hours (ambient temperature
                   dependent) no longer needed
                  Operators print sensor status page every 2 hours when ambient
                   temperature is below 40 degrees F.

16                             Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
                     Status page includes current box temperature, connectivity, and
                      battery capacity
              Safety
       ‒ iMonnit System Overview (Equipment)
           • Top/Down Equipment description:
                Network Requirements
                     Cellular
                     Wifi (Mesh system
                Ethernet Gateways
                Temperature Sensors
                     AA 3.6v lithium battery
                     Frequency Hopping Spread
                     Spectrum (FHSS) 900 MHz
                Estimated equipment cost for 320 sensors and 11 gateways was
                 approximately $62K

17                           Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.3 – Inclusion of iMonnit system as a remote
       method of monitoring the transmitter boxes.
        ‒ Temperature Sensors

        ‒ Temperature Trends

18                         Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
     • Best Practices No.3 – Inclusion of iMonnit system as a remote
       method of monitoring the transmitter boxes.

        ‒ Ethernet Gateways

19                         Forward Together • ReliabilityFirst
ERCOT/TRE Weatherization Workshop
       ‒ iMonnit System Platform
           • Internet
                 Mesh System
                         Independent of business network
                         Setup behind its own firewall
           • iMonnit Portal
                 Web-based Interface
                 Annual subscription is approximately $600 for up to 500 sensors
                 Subscription allows facility to poll each sensor every 10 minutes
                         One-minute polling option is available at extra cost
                 Interface allows:
                           User to import maps
                           Make global or individual changes to sensor settings
                           Trend sensor data
                           View battery life and connectivity
                           Creation of event email notifications

20                                 Forward Together • ReliabilityFirst
Cold Weather Preparedness SAR Update
 Common themes:
     • A continent-wide NERC Cold Weather Standard is not needed.
        ‒ SAR DT: The new standard will allow different levels of cold weather preparation to be
          implemented across the ERO due to varying climates and cold weather conditions. It is
          expected that generation located in northern areas of the country will require more extensive
          and comprehensive cold weather preparation plans as compared to west coast or
          southeastern-based generating units. These geographic differences including various plant
          configurations will be taken into consideration. Exempting certain generator types or
          geographical locations will also be considered by the SDT.
     • Data requirements are already addressed in existing standards such as EOP,
       IRO and TOP.
        ‒ SAR DT: Although these standards are associated with data requests, it is clear that the
          reliability impacts of cold weather conditions were:
            • Not thoroughly and effectively considered, or
            • Insufficient data existed, or
            • The data was not effectively utilized
21                                         Forward Together • ReliabilityFirst
Cold Weather Preparedness SAR Update (cont’d)
        ‒ SAR DT: While IRO-010 and TOP-003 broadly cover the data needed to perform "its
          operational functions", this SAR is specific to cold weather data needed for TOP, BA, and RC
          to perform regional planning and operational analysis. The format of receiving this data is yet
          to be determined but would provide a reliability impact assessment specific to cold weather
          events. The existing mandated NERC standards would be reviewed by the SDT for any
          inclusion of regional specifications of cold weather assessment requirements and revised if
          possible to reflect the information needed for regional reliability assessments. Also, the SDT
          will consider the work of the Standards Efficiency Review (SER) Phase 2 team to avoid
          duplication of efforts.

     • Market rules will correct for generator unavailability or under performance.
        ‒ SAR DT: The market can be a driving force by utilizing incentives and penalties as a means
          to ensure market participants are held accountable to their day-ahead commitments, but the
          market does not specifically address the roles and responsibilities of those entities involved
          with cold weather-related data and plant readiness requirements. Also, market rules,
          ISO/RTO policies, interconnection agreements, and PUC rules fall under Item 3 of the three-
          pronged approach per Recommendation 1 of the South Central Cold Weather Event report.

22                                      Forward Together • ReliabilityFirst
Cold Weather Preparedness SAR Update (cont’d)

     ‒ One of the Regional Winter Readiness Outreach programs has observed that
       market incentives have created both positive and negative effects:
        • Positive: To ensure availability and improve performance, entities are incorporating new
          technologies to their generating facilities. As an example, due to power block trips and
          derates caused by snow and ice accumulation on the combustion turbine inlet filters, a
          generator owner replaced the single inlet air filter box configuration with a new tri-inlet
          box design which also allowed for the installation of a hot air bleed system utilizing high
          temperature air from the combustion turbine to melt snow and ice from the filter medium.
        • Negative: Freezing of feedwater and attemperator lines have occurred due to entities
          waiting for days during cold weather conditions for the market to schedule their
          generation. They took no action to pre-warm, promote flow through or drain the piping,
          contact the BA, or self-schedule their facility.

23                                  Forward Together • ReliabilityFirst
Cold Weather Preparedness SAR Update (cont’d)

     • The need for accurate cold weather temperature design specifications or
       historical demonstrated performance and operating limitations during cold
       weather
        ‒ During the 2011 Southwest Cold Weather Event, BAs, RCs and generators often
          lacked adequate knowledge of plant temperature design limits, and thus did not
          realize the extent to which generation would be lost when temperatures dropped. It
          was recommended that the RC/BA have available:
           • The design temperatures of all generation resources.
           • Take into consideration as an extreme weather event approaches which plants will not be
             available based on their design temperature limits.
           • Commit, for purposes of serving load and being counted as reserves, only those plants
             whose temperature design limits fall within the forecasted temperature range.

24                                   Forward Together • ReliabilityFirst
Cold Weather Preparedness SAR Update (cont’d)
     ‒ As a result of the 2014 Polar Vortex, it was recommended that entities review the winter cold
       weather temperature design basis for their generating units to determine if improvements are
       needed, while ensuring that the generating unit’s ability to withstand higher temperatures in
       the summer is not compromised.
     ‒ The 2017 South Central Cold Weather Event indicated that the ambient temperature design
       rating of a generating unit was an important aspect of preparing for winter weather and
       severe cold weather events, because it specified the temperature(s) at which the unit’s full
       output can be achieved. It was noted that some entities did not know their units’ ambient
       temperature design ratings, or did not incorporate those ratings into their freeze protection
       measures.
     ‒ Since the SAR DT was made aware that certain RTO/ISO winter readiness outreach
       programs have determined that plant minimum ambient design temperature may not relevant,
       the SAR DT may consider removing the requirement for GOs/GOPs to provide temperature-
       related design information or historical cold-weather performance information. It appears that
       adequate maintenance of freeze protection could be more important in improving the
       reliability of generating units during cold weather.

25                                  Forward Together • ReliabilityFirst
Questions & Answers
      Forward Together                              ReliabilityFirst

26

              Forward Together • ReliabilityFirst
You can also read