BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...

 
CONTINUE READING
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
BUILDING CONSENT
APPLICATION GUIDANCE

We are Local Government
WWW.MSTN.GOVT.NZ
                          1
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
2
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
CONTENTS

Building Legislation.................................................................................... 2

Consent Processing................................................................................... 6

The Inspection Process............................................................................. 12

Commercial and Industrial Properties...................................................... 16

Complaints................................................................................................ 19

Aditional Information................................................................................ 21

                                                                                                                1
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
BUILDING LEGISLATION

    THE BUILDING ACT                                    WHAT IS A BUILDING CONSENT?
    The Building Act 2004 provides for the              A building consent is the formal approval
    regulation of building work, the establishment      issued by a building consent authority stating
    of a licensing regime for building practitioners,   that certain works, if properly constructed in
    and the setting of performance standards, to        accordance with the plans and specification
    ensure that:                                        will comply with the requirements of the New
                                                        Zealand Building Act, Building Regulations and
    yypeople who use buildings can do so safely
                                                        the Building Code. You cannot undertake any
      and without endangering their health;
                                                        building work which requires a building consent
    yybuildings have attributes which contribute        without this approval. Most building work
      appropriately to the health, physical             requires a building consent, but some minor
      independence, and well-being of the people        work is exempt under Schedule 1 of the Act
      who use them;
    yypeople who use a building can escape from
      the building if it is on fire; and
                                                        WHEN IS A BUILDING
    yybuildings are designed, constructed, and
                                                        CONSENT REQUIRED?
      able to be used in ways which promote             A building consent is required before you
      sustainable development.                          undertake any building work, such as additions
                                                        alterations or constructing new buildings,
    To achieve this purpose, the Act requires
                                                        and pool barriers, unless exempt. Please
    anyone proposing to do certain building work
                                                        view the Ministry of Business, Innovation and
    to obtain a building consent from a Building
                                                        Employments guidance publication “A guide to
    Consent Authority (BCA) before commencing
                                                        building work that does not require a building
    building work, with the option of obtaining a
                                                        consent” at their web site www.building.govt.nz.
    Project Information Memorandum (PIM).
    The Ministry of Business, Innovation and
    Employment (MBIE) provide a guide for when
    a building consent is not required. This can be
    viewed at their website www.building.govt.nz

2
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
It is the owner’s responsibility to check that
BUILDING ON LAND SUBJECT TO                          the tradespeople doing and or supervising the
NATURAL HAZARDS:                                     work are licensed building practitioners.
Where Council identifies that the land on which      Restricted work is work on homes and small-
the work is proposed is subject to natural           medium sized apartment buildings that is
hazards, Council will consider if the work           critical to the integrity of the building.
is major or minor and what affect the work
                                                     An exemption is available to owner-builders
will have on the hazard. Depending on the
                                                     (do-it-yourselfers) allowing them to carry out
circumstances the consent could be refused,
                                                     Restricted Building Work (RBW) on their own
granted subject to a condition that a natural
                                                     home and build their own home. There are
hazard notification is placed on the title (This
                                                     certain criteria for this and details can be
will incur additional fees) or no additional
                                                     found in the document ‘Obligations and
action could be necessary.
                                                     Responsibilities of Owner-builders and Their
Council will discuss with you the refusal            Building Project’. This document can be viewed
or notification process if this relates to           at www.building.govt.nz.
your consent.
                                                     Building consent applications are not accepted
                                                     unless they include a Memorandum -Certificate
WHAT IS RESTRICTED BUILDING                          of design work from a LBP certifying that the
                                                     design work complies with the Building Code.
WORK AND WHO ARE LICENSED
                                                     Licensed Building Practitioners (LBP) will
BUILDING PRACTITIONERS?                              also need to provide a Memorandum -
Restricted building work is work that                Record of Building Work when the work has
must be completed by or supervised by, a             been completed.
licensed building practitioner (LBP). Building       Further information can be found at
Practitioners are licensed by the Ministry of        www.building.govt.nz.
Business innovation and Employment
This ‘restricted building work’ applies to, but is
not limited to:                                      WHAT IS A BUILDING
yyFoundations;                                       CONSENT AUTHORITY?
yyFraming;                                           Building consent authorities are regional or
                                                     territorial authorities or private organisations
yyRoofing;                                           registered under section 273 of the Building
yyCladding; and/or                                   Act 2004, and are responsible for performing
                                                     building control functions under Part 2 of
yyActive fire safety systems in small-medium
                                                     the Act.
  sized apartment buildings
Licensed Building Practitioners include, but
are not limited to:
yyDesigners;
yyCarpenters;
yyRoofers;
yyExternal Plasterers;
yyBricklayers; and/or
yyBlock layers.
Registered architects, chartered professional
engineers and plumbers are deemed to be LBPs.

                                                                                                        3
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
WHAT IS A PROJECT INFORMATION                      THE MEMORANDUM ALSO INCLUDES:
    MEMORANDUM (PIM)?                                  Confirmation, subject to other provisions of the
                                                       Act that you may carry out the building work
    A project information memorandum (PIM) is a
                                                       subject to
    memorandum issued by the Territorial authority
    (Council) under sections 32 - 35 of the Building   yythe requirements of the building consent, and
    Act 2004 which sets out information relevant to    yyall other necessary authorisations
    your building work.                                  being obtained.
    This is information on special land features,      Copies of other information that may have
    including potential:                               some design impact on your proposed building
    yyerosion;                                         work like:
    yyavulsion (removal of land by water action);      yyDrainage plans;
    yyfalling debris;                                  yyWater supply plans;
    yysubsidence;                                      yyOther utility plans; and/or
    yyslippage;                                        yyAny other information that Council holds that is
                                                         relevant to your project.
    yyalluvium (the deposit of silt from flooding);
                                                       Important:
    yythe presence of hazardous contaminants
                                                       A PIM does not give any form of approval under
      which are known to Council which are likely
                                                       the District Plan or Building Act. Contact the
      to be relevant to the design, construction or
                                                       Masterton District Council’s planning department,
      alteration of your proposed building;
                                                       or your own planning adviser to determine that
    yydetails of stormwater or wastewater utility      your proposal complies with the District Plan. If
      systems which relate to your proposed building   it does not, and resource consent is required, you
      work, or are adjacent to your building site.     are strongly advised to obtain this before seeking
    A PIM also identifies any additional approvals     building consent to avoid possible expensive
    required such as:                                  changes to your proposal.

    yyResource Management Act;
    yyNew Zealand Historic Places Trust (heritage
      buildings/sites);
    yyFire and Emergency New Zealand (FENZ).

4
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
MUST I APPLY A PIM?                                   HOW LONG DOES IT TAKE TO GET A
No, PIM’s are voluntary. They may be applied          BUILDING CONSENT?
for separately or in combination with your
                                                      Building consent processing time depends on
building consent.
                                                      the complexity of your project and whether
                                                      or not you have provided all site specific
HOW TO APPLY FOR A PIM                                information. Council is required to grant the
                                                      building consent within 20 working days.
An application for a PIM must be made on the          However, if information is found to be lacking,
application form available from the Masterton         the time clock is suspended and not restarted
District Council or visit our website mstn.govt.nz    until all the requested information is provided.
This form must be completed in full, and
signed and dated before being submitted. To
submit your PIM application, please email to          HOW DO I APPLY FOR A BUILDING
buildingadmin@mstn.govt.nz. If you are unable         CONSENT?
to submit your application electronically, please
                                                      You need to complete an application form and
contact the Building Team on 06 370 6300 to
                                                      provide information relevant to your building
discuss your options.
                                                      project. You can access the forms from either:
                                                      yyour website www.mstn.govt.nz , or
DOCUMENTATION REQUIRED                                yycollect from Council offices at 161 Queen Street.
All applications must be accompanied by a
copy of:
yya site plan;
                                                      HOW DO I LODGE AN APPLICATION?
                                                      Once you have gathered all the necessary
yyfloor plan;
                                                      information, you can email the application to
yybuilding elevations;                                buildingadmin@mstn.govt.nz. If you are unable
yysite access; and                                    to submit your application electronically, please
                                                      contact the Building Team on 06 370 6300 to
yydrainage plan.                                      discuss your options.
                                                      It is important to ensure that the designer
HOW LONG DOES IT TAKE?                                provides site and project specific
                                                      documentation that clearly show Building Code
Council is required to issue the PIM within 20
                                                      compliance. Poor quality applications may delay
working days of the application being received.
                                                      your consent.
In most cases the BCA gathers PIM information
in order to process your building consent.            Please note: When emailing an application
                                                      please use dropbox (or similar) to submit large
Please note:
                                                      files. Always follow up your submission with an
Providing all fees are paid, the PIM will be
                                                      email requesting confirmation of receipt.
posted or emailed to the applicant when it is
issued. If the PIM is applied for with the building
consent, the timeframe for issue of both is 20
working days.

                                                                                                            5
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
CONSENT PROCESSING
                                                          Requests for additional information will
    HOW IS MY APPLICATION PROCESSED?                      generally be sent to the person responsible for
    All applications, regardless of how they are          the consent. Often clouding the area of drawings
    received, are vetted to check if all information      that have changed in response to an RFI, may
    has been provided, this is not a technical check.     help speed up the processing of your consent
    Your application may be rejected at this time, if
                                                          Once all disciplines involved in the process are
    insufficient information has been provided.
                                                          satisfied with compliance, a final check is made
    Providing key aspects of the application form         to ensure all work has been assessed correctly
    have been completed, the application will             before the building consent is granted pending
    be entered into the system as lodged. The             payment of fees.
    BCA has 3 days to vet the application and
                                                          The granting of the consent shows that the
    either request further information or formally
                                                          building consent authority (BCA) is satisfied
    receive the application. The 20 working day
                                                          on reasonable grounds that if the project is
    clock commences from the date a complete
                                                          constructed in accordance with the approved
    applicaiton is received. This will be the date the
                                                          plans the project will comply with the Building
    application was lodged or, if further information
                                                          Act, Building Code and Regulations.
    is required, the date that the information is
    received. The application is then allocated
    to the various disciplines within the building        PAYMENT OF FEES
    consent authority for processing, i.e. Planning,
                                                          When the building consent has been granted, an
    Building and Assets. Each discipline will review
                                                          invoice will be generated and sent to the person
    your application and assess it for compliance
                                                          indicated on the application form. It is extremely
    against the requirements of the Building Code
                                                          important to use the correct reference when
    as prescribed in the Building Act. If there are any
                                                          paying the invoice.
    questions or concerns, you will be requested to
    supply further information/clarification. The 20      Once payment has been received, the building
    working day time clock is suspended until this        consent will be issued.
    information is provided
    in full.

6
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
RECEIVING YOUR BUILDING CONSENT?
Your building consent and approved plans along
with any supporting documentation will be
sent via a dropbox link to the property owner
or nominated person. You will be advised to
download and securely save the documents as
the link will be deleted in 10 days.
If your application has been refused, a letter will
be sent advising you the reasons.
Work cannot start until the building consent has
been granted.

EXTERNAL PARTIES
Some commercial project may need reviewing
by the Fire and Emergency New Zealand - Fire
Engineering Unit. They have 10 days to provide
feedback. Your fire designer should notify you
of this, if needed, and this should be clearly
identified in the consent documentation.
In some cases the BCA may send applications
externally for review, in particular for
engineering or fire peer review. When busy,
the BCA may also send consents to external
contractors to process your consent.

HOW LONG IS MY BUILDING CONSENT
VALID FOR?
The Building Act provides that if work to which
the consent relates hasn’t started within 12
months from the date of the issue of the consent
the consent will lapse and be of no effect. This
means that you will need to apply for a
new consent.
If a CCC application has not been made by the
2 year anniversary of the grant of the building
consent, the BCA is required to make a decision
on whether or not to issue a CCC.
In either case the BCA will try to contact you to
remind you of these provisions
If the project has been delayed, you may apply
for an extension to this time.

                                                      7
BUILDING CONSENT APPLICATION GUIDANCE - We are Local Government WWW.MSTN.GOVT.NZ - Masterton ...
3. Specifications (1 complete set) -
    WHAT SORT OF INFORMATION DO                              Specifications must be relevant to the
    I NEED?                                                  particular building and to the plans
    Building consent applications can be complex.            submitted. They must give a full description
    We recommend that you engage a professional              of the type, size and grade of materials to
    person to help with the design work and drawings.        be used, and the method of construction,
    Each application must be accompanied by                  including other trade section.
    the information requirements identified in the        4. Snow Loads and Wind Zones – The Mackenzie
    application pack which includes: -                       District has extreme weather conditions
    1. Certificate of Title – 1 copy - no older than         that must be taken into consideration for all
       3 months old. Please include any Consent              building undertaken with the district. Please
       Notices listed under Interests.                       refer to Appendix 1 and 2 at the end of the
                                                             document for guidance on snow loads and
    2. Plans – (one complete set)                            wind zones. Please contact the Building
       2.1. Site Plan - Scale 1:200 (recommended             Control team on 03 685 9010 if you have any
            scale). The site plan must show the              questions relating to snow loads and
            proposed building work in relation to the        wind zones.
            property boundaries, existing buildings,      5. Engineering calculations/fire report (if
            drainage and water supply systems, spot          applicable) – (one complete set) If designs are
            levels and datum.                                from a CPEng engineer a site/project specific
       2.2. Floor Plan - Scale 1:100. To be fully            PS1 will be required.
            dimensional, including wall and partition     6. Alterations to existing buildings - Under
            sizes, designation of rooms, doors and           section 112 of the Building Act, a BCA must not
            window openings, sanitary fittings, fixed        grant a building consent to alter all or part of
            units, appliances such as wood-burners,          an existing building unless it is satisfied that,
            cooking and heating units.                       after the alteration, the building will (among
       2.3. Cross Section - Scale 1:50. To show full         other things) comply as nearly as is reasonably
            details of construction of foundations,          practicable (ANARP) with the Building Code
            reinforcing, floor structure, wall and roof      provisions relating to means of escape from
            structure, insulation and height above           fire and access and facilities for persons with
            ground level.                                    disabilities. Section 112 of the Building Act also
                                                             gives TAs some powers to allow alterations to
       2.4. Elevations - Scale 1:100. Four elevations
                                                             existing buildings. (if you intend to change the
            of the proposed building are required to
                                                             use of the building different provisions apply)
            show all doors, windows, roof heights and
            external materials and finishes.                 To determine whether an existing building
                                                             will comply ANARP with Building Code
       2.5. Drainage Plan - Scale 1:200. To show
                                                             requirements for means of escape from fire
            means and location of sewage and
                                                             and access and facilities for persons with
            stormwater disposal systems and any
                                                             disabilities after the proposed building work
            existing drains on site. Water supply
                                                             has been carried out, BCAs and TAs will need
            details must be shown. (Only a certifying
                                                             information on the building’s current level
            plumber/craftsman drain layer or
                                                             of compliance.
            licensed person working under their
            supervision can carry out plumbing/           7. Wall bracing layout (if applicable) - (1 set)
            drainage works.)                              8. Roof truss (if applicable) – (1 set)
       2.6. Details – Scale 1:5. These are generally         Manufacturer’s Truss Design and
            structural and weathertightness details          Producer Statement
            to show how the critical elements of the      9. E2 risk matrix (demonstrating
            building work are to be constructed.             weathertightness features) - (1 set).
                                                          10. H1 analysis (demonstrating insulation
                                                              requirements) (1 set)

8
CHANGE OF USE, EXTENSION OF LIFE                   IS THERE OTHER INFORMATION THAT I
AND SUBDIVISIONS:                                  MIGHT NEED?
If you intend to change the use of the building    New Vehicle Access - Any building which
extend the life, or subdivide you may need to      requires a new vehicle access must be approved.
seek professional help with the application        Contact the Council Assets and Operations
or come and speak to us about the type of          Department on 06 370 6300 to discuss this.
information you may need to supply.                A detailed plan showing the location of the
                                                   proposed access will need to be supplied with
                                                   your application.
WHAT IF MY APPLICATION IS FOR A
                                                   RAPID Number - Each new dwelling within the
HEATING APPLIANCE ONLY?                            rural area is required to have a number at the gate
You must complete the Building Consent             similar to street numbers in town. This is essential
Application form and provide all the relevant      and particularly helpful in emergencies.
information regarding the heating appliance,
such as the make, model and year of
manufacture and a copy of the manufacturer’s
                                                   WHAT ABOUT A RESOURCE CONSENT?
installation instructions. You must also supply    Some proposals require a land use resource
a complete floor plan of the building indicating   consent. If you are unsure if your proposal
where the appliance is to be fitted and showing    requires a resource consent, you can discuss
the location of the smoke detectors. Also show     the details with the planning department at the
evidence that the fireplace complies with the      Masterton District Council. Please phone
emissions regulations, www.ecan.govt.nz/data/      06 370 6300 and ask for the Planning Department.
authorised-burners.

WHERE CAN I GET A CURRENT
CERTIFICATE OF TITLE?
Contact Land Information New Zealand on 0800
ONLINE/0800 665 463 or www.linz.govt.nz

                                                                                                          9
HOW MUCH WILL MY BUILDING
     CONSENT COST?
     This depends on the type of application, cost of
     work involved and the level of detail provided.
     Charges are based on the length of time it takes
     to process an application and include costs
     such as:
     yylevies payable to the Ministry of Business
       innovation and Employment (payable on all
       applications $20,444 or more);( Building Levy
       Order GST inclusive)
     yylevies payable to BRANZ (payable on all
       applications $20,000 or more);
     yytime spent processing the application;
     yyinspections (type and number vary depending
       on application);
     yyissue of code compliance certificate (CCC);
     yyissue of compliance schedule (if applicable);
     yyvehicle crossing (if applicable); and
     yywater meter connection (if applicable).
     A schedule of fees is available from our website
     www.mstn.govt.nz, or collected from Council
     offices at 161 Queen Street. Fees can be paid at
     the office or by internet banking.
     If you choose to withdraw your building
     consent application once processing has
     started, you will be charged for time spent and
     administration costs.
     If your building consent application is refused
     once processing has started, you will be charged
     for time spent and administration costs.
     The BCA may charge additional fees for
     processing time where an unreasonable amount
     of time has had to be spent processing the
     consent or for additional inspections.

     WHO ARE THE BUILDING RESEARCH
     ASSOCIATION OF NEW ZEALAND
     (BRANZ) AND WHY IS MY
     APPLICATION LEVIED?
     BRANZ Limited is an independent and research,
     testing, and information resource for the
     building and construction industry. Further
     information at: www.branz.co.nz

10
may be able to be approved on site by
WHO ARE THE MINISTRY OF BUSINESS,                     the inspector
INNOVATION AND EMPLOYMENT (MBIE)?                     There may be a cost involved in approving the
MBIE is the government department responsible         minor variation.
for regulating the building industry.

                                                      WHAT ARE BUILDING
CAN I CHANGE MY PLANS LATER?                          CONSENT CONDITIONS?
Yes, if you need to change anything on your
                                                      These are conditions imposed on your building
plans, you must apply for an amendment before
                                                      consent which are deemed necessary to ensure
carrying out any changes to your approved plans.
                                                      compliance. For example, all building consents
At the end of the building project, the approved
                                                      are issued subject to the condition that officers
building consent documentation needs to be an
                                                      of the building consent authority are entitled at
accurate reflection of what has actually been
                                                      all times, during normal working hours, or while
built. Changing the details of the original consent
                                                      work is being done, to inspect building work
drawings can be completed in two ways via either
                                                      which is being carried out. Other conditions
a site variation or an amendment. If you have
                                                      may be in relation to building on a site subject to
made changes without approval the BCA may
                                                      specific hazard conditions or building over two
stop your job until the changes are resolved.
                                                      or more allotments for example.

AMENDMENTS                                            WHAT ARE BUILDING CONSENT
Amendments are those where work is outside
the scope of the original consent e.g. additional
                                                      ENDORSEMENTS/ADVICE
footprint or increases in floor area, construction    NOTES/REMINDERS?
method, and significant changes to layout. An         Building consent documents are often endorsed
amendment form is required to be completed            or have notes added by the consenting authority
and fees payable.                                     to remind the building owner about specific
                                                      aspects of construction to achieve compliance.
MINOR VARIATIONS                                      For example a note may be added regarding
                                                      specialist inspections that may be required.
Minor variations are changes that do not usually      These endorsements will be noted on the actual
affect compliance with the Building Code e.g.         consent. It is important that you read and
changes to types of taps, the position of kitchen     understand all endorsements of the building
joinery, and non-structural walls or doors. You       consent before commencing work. If you do not
may need to provide information to record the         understand any endorsement imposed, please
change however it is not necessary to complete        contact us to discuss.
a new building consent application form. This

                                                                                                            11
THE INSPECTION PROCESS
                                                           In some cases commercial finals will require
     WHEN CAN WORK BEGIN?                                  two inspectors to undertake the inspection and
     Although work can begin when you have                 review specified systems.
     received your building consent, if a resource
                                                           Nonstandard inspection types will be noted on
     consent is required, you may need to wait until
                                                           the inspection list for your consent
     that is also issued.
                                                           Sometimes it is necessary for specialists
                                                           to conduct inspections in addition to the
     WHAT INSPECTIONS DO I NEED?                           inspections carried out by the Building Consent
     In most cases a building officer from Council will    Authority (BCA). If a specialist inspection
     need to visit the building at various stages during   is necessary you will be advised before the
     the work to ensure work complies with the             consent is issued. Generally, these inspections
     consent. Typically the inspector will record the      are necessary to confirm ground stability or
     inspection by making notes and taking photos.         specific design by a registered engineer.
     When your application is processed, the building      It is the owner’s responsibility to ensure that the
     officer will determine what inspections are           BCA is contacted at the appropriate times to
     necessary. Each inspection will be identified on      undertake the required inspection. The Building
     your site check sheet attached to your building       officer will email a copy of the inspection sheet
     consent. Typical inspections may include but          to the contact person.
     not limited to foundations, concrete masonry,         Please ensure you read inspection requirements
     concrete floor slab, pre-cladding, cladding, pool     and are familiar with them before commencing
     fencing, wet area membranes and fireplaces,           work. If in doubt, please ask.
     pre-line building and plumbing, post-lining,
     drainage and a final.                                 Missed inspections may mean that a CCC cannot
                                                           be issued.

12
HOW DO I BOOK AN INSPECTION?                        WHAT IF THE INSPECTION IS
Building inspections are booked through the         NOT APPROVED?
administration team by phoning 06 370 6300 (do
                                                    If the inspection fails, the work to be fixed
not contact the building inspectors directly).
                                                    will be recorded on the site inspection sheet.
Inspections are undertaken Monday - Friday
                                                    Another inspection will be required to inspect
9.00am to 3.00pm (excluding public holidays).
                                                    the remedial work. In some cases work may have
Fixed time inspections are completed under
                                                    to stop, in others some work may be allowed
special circumstances.
                                                    to continue or an amendment may need to be
You must provide the following information when     applied for. If the work is not remedied to the
booking an inspection:                              satisfaction of the building officer, it is possible
yysite address;                                     that a Notice to Fix (NTF) will be issued.

yybuilding consent number;
yyname and telephone number of contact person
                                                    RE-INSPECTIONS MAY INCUR
  on site;                                          ADDITIONAL CHARGES.
yyEmail address of where the site inspection        Please note that building control officers may
  result will be sent to.                           refuse to complete the inspection if the site is
                                                    seen to be unsafe.
yydate and time the inspection is required; and
yyType of inspection, ie plumbing, drainage,
  foundation, pre-slab, pre-line, etc.              WHAT IS A NOTICE TO FIX (NTF)?
yyIf RBW please provide the names of any            A NTF is a formal notice issued by the building
  relevant LBP’s including licence references       consent authority advising that certain works
                                                    have not been carried out in accordance with
Please Note                                         the building consent or the Code/Act. If an NTF
It is your (or your builder’s) responsibility to    is issued you must address the issues identified
notify Council a minimum of 24 hours before you     within the prescribed timeframe to prevent
require an inspection.                              further action being taken. Typically an NTF
                                                    will be issued for serious or ongoing breaches.
HOW DO I KNOW IF THE INSPECTION                     If a notice to NTF is issued, documentation
                                                    identifying and explaining the process will
HAS BEEN PASSED?                                    accompany it. We would prefer to work with you
At the conclusion of all inspections the outcome    to get compliance.
of the inspection is recorded on the site
inspection sheet and emailed to the nominated
person. It is recommended that the owner or an
agent is available on site for all inspections to
ensure they are clear on the outcome.
You may be asked to stop work or continue
with conditions (conditional continuation) if the
inspector fails the inspection or work is non-
compliant or unsafe.
Please Note
No plans and documentation on site -
No inspection.

                                                                                                           13
DO I NEED A FINAL INSPECTION?
     Yes, all building consents require a final
     inspection. The purpose of the final inspection is
     to ensure that all work is completed to the extent
     required by the Building Consent.
     Although there is no imposed time frame on
     an owner to complete work, on the 2 year
     anniversary of the granting of your consent the
     BCA is required to decide if a CCC can be issued.
     If you cannot complete the work within this
     timeframe, it is essential that you contact us to
     discuss time frames.
     An owner must apply for a CCC once all the work
     described in their building consent is completed.
     To make an application you must complete a CCC
     application form including filling in details of who
     did the work and when the work was completed
     This can be found on the Building and Planning
     page on our website www.mstn.govt.nz.
     Once the application has been made the BCA
     has 20 working days to decide whether to issue
     a CCC. The BCA will complete an inspection, if
     a final inspection has not already occurred, and
     ensure all documentation has been received.
     The required documentation will be listed on the
     building consent If all building work complies
     and documentation supplied a code compliance
     certificate may be issued. If CCC cannot be
     issued the 20 working day clock is stopped and
     further information sought or the CCC will
     be refused.
     The CCC can only be issued where the BCA is
     satisfied on reasonable grounds that the work
     complies with the consent

     WHAT IS A CODE COMPLIANCE
     CERTIFICATE?
     A Code Compliance Certificate (CCC) is the
     final certification confirming that the BCA is
     satisfied on reasonable grounds that all works
     undertaken complies with the building consent.
     You must apply for a CCC after all work has been
     completed. This is an important document and
     should be retained for future reference.
     A CCC can be withheld until any outstanding fees
     for the likes of additional inspections etc. Fees
     can be paid by internet banking or at the
     Council offices.

14
Please note:
PRODUCER STATEMENTS                                 It is strongly recommended that you check with
In some case the BCA may accept a producer          the building department to ensure the engineer
statement from a suitably qualified person          you are using is competent to do so.
verifying compliance with the Code or consent.
                                                    Identified also are additional inspections
A producer statement (expert opinion) for           required by the suitably qualified
design (PS 1) has, in the past, been accepted       independent design professional that are to
in the processing of a Building Consent which       be carried out along with and including BCA
clearly identifies the intent of the design and     inspection requirements.
construction details required for completion.
                                                    A Construction review PS4 (statement of expert
Some details of your building consent may be        opinion) will be required to be issued by the
required to be peer reviewed by a Chartered         agreed suitably qualified independent design
Professional Engineer (CPEng). A Producer
                                                    professional where requested prior to issuing a
Statement (PS2 Design Review) will be required
                                                    Code Compliance Certificate. It must state that
to be supplied from the CPEng.
                                                    the building was constructed as per the building
 Council can complete this process for you or       consent documents and be accompanied by
you can elect to have the structural design         copies of all inspection reports and site notes
reviewed by your own engineer. All costs are the    for the project made during construction of the
responsibility of the owner.                        building works.
Below are details for when a peer review is or
isn’t required:
                                                    SITE SAFETY FOR INSPECTORS
yySimple designs to NZS3604 i.e. bracing,
                                                    You are responsible for the safety of visitors
  foundations would not need to be reviewed.
                                                    to the work site including those undertaking
yySimple steel beams (with good connection          building inspections. You must provide safe
  details shown) would also not need to be          access to parts of the construction necessary
  peer reviewed.                                    for inspection. Ladder access must be securely
yySheds with an importance level 1 and in a rural   founded and tied. Scaffold access and roof edge
  situation i.e. hay sheds do not need to be        protection is generally required. Inspectors will
  peer reviewed.                                    not inspect unsafe sites.
yyA shed with an importance level 2 and to be
  used for residential dwellings do need to be      WHAT ARE MULTI-PROOF APPROVALS?
  peer reviewed.
                                                    Multiproofs are issued by the National Multiple-
yyComplex designs outside the scope of              Use Approval Service of the MBIE. A multiproof is
  NZS3604 and structural designs completed          a statement by the Ministry that a specific set of
  by an engineer that isn’t a CPEng, whether        building plans and specifications complies with
  deemed simple designs or not, would need to       the New Zealand Building Code (NZBC).
  be peer reviewed and a PS2 would need to be
  supplied with the building consent.               A MultiProof is not, and does not replace, a
                                                    building consent. The holder of a MultiProof
If you choose to have the design peer reviewed
                                                    must obtain a building consent each time
using your own engineer please ensure that the
                                                    they wish to construct the design to which
engineer who completes the peer review (and
                                                    the MultiProof relates. The BCA will only need
provides the PS2) is a Chartered Professional
                                                    to assess the Building Code compliance of
Engineer (CPEng) and has the correct
                                                    site-specific features that are excluded from
competence to complete the review. Council will
                                                    the MultiProof, the BCA has 10 Days to issue a
require evidence that the engineer is a CPEng
and that their area of expertise is suitable to     MultiProof consent.
complete the review of your design.
These details can be found at www.ipenz.org.nz
or by contacting the Institution of Professional
Engineers (IPENZ) on 04 473 9444.

                                                                                                         15
COMMERCIAL AND
     INDUSTRIAL PROPERTIES
     SECTION 363 PUBLIC PREMISES                            WHAT ARE PUBLIC PREMISES?
     It is the owner’s decision as to when a building       Any building which is open to the public
     can be occupied however, if your building is           whether free of charge or by payment of a
     open to the public, whether free of charge or          charge, including:
     by payment of a charge, the building cannot
                                                            yyshopping malls;
     be used or occupied until a Code Compliance
     Certificate (CCC) is issued.                           yycinemas;

     In certain circumstances it may be possible            yymarae
     to apply for a Certificate for Public Use (CPU),       yycamping grounds
     which will allow a building or part of a building to
     be used before the Code Compliance Certificate         yyvisitor accommodation
     is issued. Each application will be considered on        garages and workshops;
     a case-by-case basis.                                  yyfuneral homes;
                                                            yyoffice and retail complexes; and
                                                            yyrest homes, etc

16
WHAT IS A COMPLIANCE                                 WHAT IS A COMPLIANCE SCHEDULE
SCHEDULE (CS)?                                       STATEMENT?
A Compliance Schedule is a document issued           A compliance schedule statement is issued
by the building consent authority for buildings      by the Building Consent Authority (BCA) and
which contain specified systems. Specified           serves as temporary notification of Compliance
systems include:                                     Schedule (CS) requirements. It will list the
                                                     inspection, maintenance and reporting
yyautomatic systems for fire suppression;
                                                     procedures necessary to keep the specified
yyautomatic or manual emergency warning              systems in good working order. It is issued at the
  systems for fire or other dangers;                 same time as the Code Compliance Certificate
yycable cars.(residential dwellings)                 (CCC). It must be replaced in 12 months with a
                                                     Building Warrant of Fitness (BWOF), which is
yyemergency lighting systems                         issued by the building owner.
yylaboratory fume cupboards
yysmoke control systems                              HOW DO I OBTAIN A
yyother fire safety systems or features (systems     COMPLIANCE SCHEDULE?
  for communicating information intended
  to facilitate evacuation, final exits, fire        A compliance schedule must be applied for at
  separations, signs);                               the same time a building consent application is
                                                     made and will be issued with a Code Compliance
yyemergency power systems for, or signs              Certificate (CCC) by the Building Consent
  relating to, a system or feature specified for     Authority (BCA) for:
  any of the above
                                                     yynew buildings (if the building has one or more
yymechanical ventilation or air conditioning           specified systems); or
  systems
                                                     yyan upgrade to an existing building or systems,
yyelectromagnetic or automatic doors or                required as a result of a change of use or
  windows;                                             alterations, which may also require a
yyescape route pressurisation systems                  building consent.

yyriser mains for use by fire services               When applying for a CCC for a building that
                                                     contains specified systems you should attach
yyautomatic back-flow preventers connected to
                                                     to the application relevant certification for
  a potable water supply
                                                     the specified systems as well as details of the
yybuilding maintenance units providing access to     specified systems and plans showing specified
  exterior and interior walls of buildings           system locations and or layout.
yylifts, escalators, travelators, or other systems
  for moving people or goods within buildings        WHAT INFORMATION DO I NEED
yyaudio loops or other assistive                     IF I AM APPLYING FOR A
  listening systems
                                                     COMPLIANCE SCHEDULE?
A compliance schedule must be kept on site and
made available to building officers, Independent     Your architect/designer should provide you
Qualified Persons (IQP’s) and authorised agents.     with information relating to the performance
                                                     standards for each specified system contained
                                                     within the building at the time the application
                                                     for building consent is made. The performance
                                                     standards will identify the inspection,
                                                     maintenance and reporting procedures required
                                                     for each system. The appropriate forms are
                                                     available from icc.govt.nz/building/sbcg-forms.

                                                                                                          17
CAN I BE PROSECUTED FOR NOT                          WHAT DOCUMENTS SHOULD I KEEP
     OBTAINING A COMPLIANCE SCHEDULE                      REGARDING THE BUILDING WARRANT
     OR IF MY BUILDING WARRANT OF                         OF FITNESS (BWOF)?
     FITNESS HAS EXPIRED?                                 You are legally required to obtain written
                                                          reports relating to the inspection, maintenance
     Yes, depending on the alleged offence, the fine
                                                          and reporting procedures of the compliance
     ranges from $20,000 to a maximum of $200,000.
                                                          schedule which must be signed by the
                                                          independent qualified persons, or licensed
     WHAT IS A BUILDING WARRANT OF                        building practitioner who has carried out any of
                                                          the listed procedures, (inspection, maintenance
     FITNESS (BWOF)?                                      or reporting).
     A Building Warrant of Fitness (BWoF), (Form
                                                          You are required to keep all reports together
     12), is a statement issued annually on the
                                                          with the Compliance Schedule (CS) for a period
     anniversary of the issue of the Compliance
                                                          of two years and produce those reports for
     Schedule by the building owner to Council
                                                          inspection when required.
     stating that the requirements of the compliance
     schedule have been fully met.
     The Building Warrant of Fitness (BWoF) must          WHAT IS AN INDEPENDENT QUALIFIED
     have attached to it all certificates of compliance   PERSON (IQP)?
     issued by the Independent Qualified Person
                                                          An IQP is a person who is qualified to carry out
     (IQP). These documents must be issued in the
                                                          any performance inspection, maintenance,
     prescribed form (Form 12A) and certify that
                                                          reporting or recommendation on a
     the inspection, maintenance and reporting
                                                          specified system.
     procedures stated in the compliance schedule
     (CS), have been fully complied with during the       All IQP’s are required to be registered with Council.
     previous twelve months.

18
COMPLAINTS
WHAT HAPPENS IF I AM UNHAPPY                       HOW DO I MAKE A COMPLAINT?
ABOUT ANY DECISION THE BUILDING                    You can make a complaint in person; however it
CONSENT AUTHORITY HAS MADE?                        must be accompanied by a written statement.
                                                   Complaints not made in writing or made
You have the right to appeal any decision the      anonymously will not be acted upon.
Building Consent Authority (BCA) has made, or to   Complaints about our BCA functions can be
complain about any building control function the   made on the following link, www.mstn.govt.nz/
Building Consent Authority (BCA) undertakes. A
                                                   make-a-complaint
customer has a right to complain and have their
complaint managed.
                                                   COMPLAINTS SHOULD BE
WHAT IS A BUILDING CONTROL                         ADDRESSED TO:
FUNCTION?                                          Planning and Building Manager
                                                   Masterton District Council
A complaint in relation to building control is     PO Box 444
defined as a complaint about:                      Masterton 5840
yymeeting statutory time frames;
yylodgement or vetting of building
  consent applications;
                                                   WHAT INFORMATION IS REQUIRED?
                                                   yydate incident occurred;
yyprocessing of building consent applications;
                                                   yynature of complaint (guidance information,
yyinspection of work under construction;
                                                     vetting, lodgement, inspection, notice
yyissuing of a notice to fix;                        to fix, code compliance certificate or
yyissuing of code compliance certificates;           compliance schedule);
yyissuing compliance schedules;                    yycopies of any supporting information (if
                                                     applicable); and
yyfailure to provide appropriate information
  or advice;                                       yyrelationship (customer, regulator,
yyfees and charges; and                              or stakeholder).

yyfailure to meet legislative or Building
  Code requirements.

                                                                                                    19
HOW LONG DOES IT TAKE?                              WHAT ELSE CAN I DO?
     All complainants will be responded to within        If you are still unhappy or choose to use an
     2 working days acknowledging the receipt of         alternative route to settle a matter of doubt
     the complaint and advising a timeframe for          or dispute, you may apply to the Ministry of
     investigation and response.                         Business, Innovation and Employment (MBIE)
                                                         for a Determination. Visit www.building.govt.
     All complaints will be acted upon within 2 weeks
                                                         nz for further information on this service and to
     of receipt of the complaint, unless a request for
                                                         download the form (Form 14).
     further information is made.
                                                         In some cases you can seek a determination
                                                         from the Ministry of Business innovation and
     DO I HAVE A RIGHT OF APPEAL?                        employment where there is a matter of doubt
     Yes, if you do not agree with the outcome you       or dispute or lay a complaint with the MBIE
     may request a review of the decision. All appeals   regarding building control function. Queries of
     must be made in writing, setting out the reasons    this nature should be made to MBIE direct
     why you disagree with the decision.

     ALL APPEALS SHOULD BE
     ADDRESSED TO:
     Chief Executive
     Masterton District Council
     PO Box 444
     Masterton 5840

20
ADDITIONAL INFORMATION
USEFUL WEBSITES/TELEPHONE NUMBERS                      USEFUL PUBLICATIONS
Ministry of Business, Innovation, and                  NZ Homeowners’ Project Workbook – Your Guide
Employment (formerly DBH)                              to Building a Better Home (order local copy at:
www.dbh.govt.nz                                        www.buildingguide.co.nz or 09 360 8885
0800 60 60 50
                                                       Guide to Applying for a Building Consent (Simple
Environment Canterbury                                 Residential Buildings) – Department of Building
http://www.ecan.govt.nz/                               and Housing
0800 324 636
                                                       The Building Act and You – Department of
BRANZ		                                                Building and Housing
www.branz.co.nz
0900 5 9090
Consumer Build (Independent advice)
www.consumerbuild.org.nz/publish
Land Information New Zealand
www.linz.govt.nz
Building Research
www.buildingresearch.org.nz
Institution of Professional Engineers of NZ
www.ipenz.org.nz
04 473 9444
Fire and Emergency New Zealand – Building Design
for Fire Safety
https://fireandemergency.nz/
Fire and Emergency New Zealand – Home Sprinklers
https://fireandemergency.nz/at-home/home-sprinklers/
NZ Homeowners’ Building Guide
www.buildingguide.co.nz
09 360 8885

                                                                                                          21
PHONE
            06 370 6300
             8am - 5pm

               EMAIL
       Council@mstn.govt.nz

             CALL INTO
      Masterton District Council
     161 Queen Street, Masterton
            8am - 4.30pm

             WRITE TO
      Masterton District Council
     PO Box 444, Masterton 5840

        WWW.MSTN.GOVT.NZ

24
You can also read