An Integrated Rail Plan
   for the Midlands
Accelerating, maximising and securing
     the benefits of HS2 Phase 2b

             August 2020
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
Making the most of HS2                                                                                             Integrated Rail Plan – the
Now more than ever, the UK desperately                    economy, maximising benefits and ensuring swift and      story so far
needs an efficient, sustainable and reliable              effective delivery.
                                                                                                                   In February 2020, after a detailed evaluation of        methodology it proposes to use to undertake its
railway network. As we move to reboot the                 As the Sub-National Transport Body for the Midlands,     the costs, benefits, challenges and opportunities       review. It also shared emerging findings from the
economy in the aftermath of COVID-19,                     Midlands Connect has worked alongside its partners       presented by the construction of our new high-speed     initial evidence gathering process. In the coming
                                                          to gather evidence, present technical expertise and      railway, Boris Johnson committed to building HS2        months, the NIC will undertake further stakeholder
investment in capital infrastructure will                 gain consensus on the priority schemes the region        in full.                                                engagement and research into potential options for
be an essential fiscal tool in supporting                 needs to make the most of HS2 and fully realise the                                                              the IRP before the final assessment is published and
employment, encouraging development and                   positive impacts it will bring. The recommendations      However, the publication of the eagerly-awaited
                                                                                                                                                                           submitted to the Department for Transport.
                                                                                                                   Oakervee Review recommended that while the
restoring business confidence.                            outlined in this submission - if integrated with our
                                                                                                                   development and delivery of Phase One (from
                                                          new high speed network - will deliver benefits sooner,
Although the last to be built, Phase 2b of High Speed
Two (HS2) is central to its purpose and success,
                                                          connect more communities, create more jobs and           London to Birmingham) and Phase 2a (from
                                                                                                                   Birmingham to Crewe) should continue as planned.              Our Submission
                                                          crucially, change more lives for the better.
linking the great cities of the North to the Midlands                                                              It was confirmed by the Prime Minister that the
                                                                                                                                                                                 Midlands Connect built consensus across its
and beyond, connecting millions more people to the                                                                 Department for Transport would develop an
                                                                                                                                                                                 partnership, which includes local enterprise
high speed network, and freeing up capacity on the                                                                 Integrated Rail Plan (IRP) to consider how both
                                                                                                                                                                                 partnerships and local transport authorities
conventional railway across the UK, to the benefit of                                                              Eastern and Western legs of Phase 2b could be best
                                                                                                                                                                                 to submit a region-wide response to the NIC’s
millions more.                                                                                                     integrated within the wider network.
                                                                                                                                                                                 call for evidence.
This is a once-in-a-generation project, one that will                                                              The National Infrastructure Commission (NIC)
                                                                                                                                                                                 The investments and interventions we
create a railway fit for the next century. We must work                                                            has been tasked with undertaking a ‘Rail Needs
                                                                                                                                                                                 have suggested form three ‘packages’ and
collaboratively and conscientiously with Government                                                                Assessment’ for the Department for Transport,
                                                                                                                                                                                 are aimed at ensuring three outcomes;
to aid the development of its Integrated Rail Plan                                                                 outlining the options for rail interventions the
                                                                                                                                                                                 accelerating the benefits of HS2 in the
which supports promises to ‘level-up’ the UK                                                                       Midlands and the North require to make the most
                                                                                                                                                                                 Midlands; maximising the positive impacts
                                                                                                                   of HS2. This assessment will inform the final IRP,
                                                                                                                                                                                 and ‘reach’ of HS2; and securing the delivery
                                                                                                                   which Government is due to publish before the end
                                                                                                                                                                                 of HS2 in its entirety.
      Sir John Peace, chairman                                                                                     of the year.
                                                                                                                                                                                 Crucially, our response provides an account
      of Midlands Connect
                                                                                                                   In early spring 2020, the NIC launched a ‘Call for
                                                                                                                                                                                 of how Phase 2b of HS2 can be fully
                                                                                                                   Evidence’; asking local authorities, businesses and
                                                                                                                                                                                 integrated with Midlands Engine Rail, our
      “The construction of High Speed Two is a                                                                     transport bodies to respond to a series of questions,
                                                                                                                                                                                 rail programme composed of seven major
      watershed moment for the UK regions, but in                                                                  and to provide the data and figures required to
                                                                                                                                                                                 interventions, including the flagship Midlands
      the Midlands, as in the North, the full benefits                                                             justify their rail investment needs. In July 2020,
                                                                                                                                                                                 Rail Hub scheme.
                                                                                                                   the NIC published an interim report setting out the
      of our transformational new railway can only
      be delivered if it is integrated with other
      strategic improvements, namely Midlands
      Engine Rail.                                                                                                                                                            Prime Minister Boris Johnson,
      The Integrated Rail Plan is our chance to reap                                                                                                                          addressing Parliament on 11th
      the rewards of a decade’s worth of planning,                                                                                                                            February 2020
      to connect more people to the high speed line,
                                                                                                                                                                              “The review recently conducted by Douglas
      and to bring benefits to local communities
                                                                                                                                                                              Oakervee leaves no doubt of the clinching
      sooner. If this Government is going to level up
                                                                                                                                                                              case for High Speed Rail.”
      the UK economy, it must heed the advice of its
      experts in the regions to deliver a truly first-                                                                                                                        “The cabinet has given high-speed rail the
      class transport network.                                                                                                                                                green signal. We are going to get this done.”
      We are committed to working with the                                                                                                                                    “Together, this revolution in local and
      Department for Transport to make this                                                                                                                                   national transport has the potential to be
      happen.”                                                                                                                                                                truly transformative for the entire country.”

  2                                                                                                                                                                                                                           3
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
The proposals and evidence submitted to
                                                     the NIC by Midlands Connect act to fulfil
                                                                                                                   Our Submission                                                                 To Scotland
                                                                                                                                                                                                                                Key
                                                     three primary ‘aims’:                                         The strategic rail needs of the
                                                                                                                   Midlands can be grouped into three                                             Newcastle
                                                                                                                                                                                                                                HS2Add a green line from Derby to
                                                     1) Accelerate the benefits of HS2                             distinct packages.                                                                                              Nottingham
                                                                                                                                                                                                                                Package West  alongside the purple
                                                     Under the delivery schedule outlined in the Oakervee                                                                                                                             but only add a green circle at
                                                                                                                                                                                                                                Package East
                                                                                                                   Package West, which utilises the high                                          Durham
                                                     Review, it is possible that the full HS2 network,             speed infrastructure delivered in Phase
                                                                                                                                                                                                                                      Nottingham station, not Toton
                                                                                                                                                                                                                                Package Connect
                                                     particularly connections from the East Midlands               One and 2a of HS2, Package East, which                                           Darlington
                                                     to the West Midlands and North of England, will               utilises the high speed infrastructure
                                                     not be up and running until 2040. To condemn                  delivered on the Eastern Leg of Phase
                                                     communities that have suffered from chronic, historic         2b of HS2, and Package Connect, which
                                                     underinvestment to a two decade wait for the benefits         seeks to improve east-west connectivity
                                                     of HS2, both in terms of connectivity, job creation           across the Midlands.                                                                       York
                                                     and associated development would be a wasted                                                                                         Leeds
                                                     opportunity and a betrayal of Government’s pledge to
                                                     ‘level-up’ the UK economy.
                                                                                                                                                               Manchester
                                                     Our Integrated Rail Plan proposals would accelerate                                                                                                Doncaster

                                                     connectivity improvements, bringing benefits to the                                                   Stockport

                                                     Midlands and the North sooner.                                                                                           Sheffield

                                                     2) Maximise the positive impacts and
                                                     ‘reach’ of HS2
                                                                                                                                                                           Chesterfield
                                                                                                                                                                                                                                      Lincoln
                                                     Although the high speed network will form the
                                                     essential backbone of our future transport network,                                                                                               East Midlands
                                                                                                                                                                                                        Hub (Toton)
                                                     there is still much work to be done to ensure                                     Crewe                                                                                    Newark Castle

                                                     widespread accessibility to this new railway. Much of                                                          Stoke-on-Trent
                                                     the investment we seek will supplement and enhance                                                                                                              Nottingham
                                                                                                                                                                                      Derby
                                                     the connectivity HS2 provides by; connecting more
Our ‘accelerate’ schemes                             people into the high speed network; using the high
                                                                                                                                                                    Uttoxeter
                                                                                                                                                                                Burton
                                                                                                                      To Wales                                                  upon                                 Loughborough
Accelerating service benefits between                speed network to run new services; or utilising                                        Wellington                          Trent                   EMA

                                                                                                                                                     Telford
Birmingham and Manchester, using new high            capacity that HS2 frees up on the existing network to                 Shrewsbury
                                                                                                                                                                           Tamworth
                                                                                                                                                                                                                       Leicester
speed track between Birmingham and Crewe             create faster, more frequent connections across the                           Wolverhampton                                             Nuneaton
built during Phase 2a, and increasing existing       Midlands.                                                                                   Sandwell & Dudley

network capacity between Crewe and Manchester.                                                                                                Birmingham                                          Interchange
                                                                                                                                                                                                                           Market Harborough

                                                     Phase 2b of HS2 must be fully integrated with                                                         Kings Norton
This would enable passengers to travel from                                                                                                                                                       Coventry                    Kettering
                                                     Midlands Engine Rail for its full benefit to be realised.
                                                                                                                                                                                      BHX
                                                                                                                                                         Bromsgrove
Birmingham to Manchester much faster than they                                                                                                                             Solihull                     Birmingham              Wellingborough

                                                     3) Deliver HS2 in its entirety
                                                                                                                                                                                                        International
can today, significantly improving journey times                                                                                               Droitwich Spa
                                                                                                                                                                            Leamington Spa
from 2029.                                                                                                                               Worcester
                                                     There is a sustained and widespread consensus                                                                     Worcestershire                                               Bedford
                                                                                                                                         Great Malvern                    Parkway
Accelerating the benefits of the Eastern Leg of      amongst the Midlands Connect partnership, that                         Hereford                                                         Banbury
HS2 Phase 2b; allowing for the commencement of       the full scope of benefits associated with our high                                         Ledbury
high speed services from Birmingham to the East      speed network can only be achieved by delivering the
Midlands Hub at Toton and on to Chesterfield,        project in its entirety, an assumption evidenced in                                                                Cheltenham Spa

Sheffield and Leeds (via a connection to the         the HS2 business case. Although we are advocating
conventional network 10 miles south of Leeds)        delivering benefits earlier we must ensure that HS2                                                                                                      Oxford

as early as 2031, deriving journey time savings,     is built all the way to Manchester and Leeds, within                                                                                                                                         Old Oak Common

increased capacity and revenue generation earlier.   the current specification, and that no measures are
                                                     taken to de-scope or scale down infrastructure. Any                     Newport
                                                                                                                                                  Bristol Parkway
                                                     omissions or downgrading of the network would               Cardiff                                                                                                                          London
                                                     undermine a decade of careful planning and dilute                                 Bristol                                                                       Reading
                                                     the benefits of this transformational scheme.

 4                                                                                                                                                                                                                                                                 5
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
Birmingham Airport Connectivity                                      Accelerate Birmingham – Manchester
                                                                                                                                                                                                                At present, there are no plans to enhance rail services
Package West:                                                                           Andy Street,
                                                                                                                                                                                To Scotland
                                                                                                                                                                                                                between Birmingham and Manchester until the

Leveraging Phase One/2a                                                                                                                                                                                         completion of the full HS2 network. In our response
                                                                                                                                                                                     Newcastle

                                                                                        West Midlands Mayor                                                                           Durham
                                                                                                                                                                                                                to the National Infrastructure Commission we have
(Incrementally delivered                                                                “The Midlands Rail Hub is a vitally-important
                                                                                                                                                                                       Darlington
                                                                                                                                                                                                                put forward a solution that could bring forward
                                                                                        project. It will transform connectivity across                                                                          significant journey time savings between these two
from 2025-2029)                                                                         the region, establishing Birmingham Moor
                                                                                                                                                                                           York
                                                                                                                                                                                                                major economic centres, before the full HS2 network
                                                                                        Street station as a major interchange, and                                                     Doncaster
                                                                                                                                                                                                                is operational. We suggest utilising the 60 miles of
                                                                                        opening up access to the new high speed                                    Sheffield
                                                                                                                                                                                                                new high speed railway between Birmingham and
                                                                                        network at Curzon Street. It’s essential that we                                                                        Crewe, built during Phase 2a, combined with a set
This package will utilise the new high speed                                            push ahead with these improvements.”                                                                                    of capacity enhancements on the existing network
infrastructure delivered in Phase One and 2a of
                                                                                                                                                                                                                between Crewe and Manchester. This combination
HS2, as well as utilising the additional network
                                                                                                                                                                                       Derby                    will mean that conventional-compatible services,
capacity HS2 will create on the conventional railway
                                                                                                                                                                                                                which run on the high speed line as far as Crewe
to improve journey times between economic centres
                                                                                                                                                                                                                then on existing track from Crewe to Manchester can
sooner, enhance local connectivity and improve
                                                                                                                                                                                                                provide much faster services than today before the
services for commuters.                                                                                                                                   Birmingham           BHX
                                                                                                                                                                                     Birmingham International
                                                                                                                                                                                                                full high speed line is up and running.
                                                                                                                                                                                       Coventry
Midlands Rail Hub                                                                                                                                                 Solihull
                                                                                                                                                                                                                The improvements will create both short-term
                                                                                                                                                                                       Leamington Spa
                                                                                                                                                                                                                benefits to inter-regional connectivity and then once
                                                                                                                                                                                 Banbury                        the full Western Leg of HS2 is complete, long-term
                                                       Derby             Nottingham                                                                                                                             benefits for commuters, with the new capacity being
                                      Burton Upon Trent                                                                                                                                                         utilised by higher-frequency commuter services in
                                                                         Loughborough                                                                                                             Oxford        Greater Manchester, which will also help to reduce
                                                Tamworth                  Leicester                                                                                                                             overcrowding in the area.
                                                              Nuneaton

                           Birmingham                                                                                                                                                                           Transport for Greater Manchester (TfGM) has led
                                 Kings Norton                                                                                                                                                       Reading     a study into rail capacity south of Manchester and
                                Bromsgrove

                             Droitwich
                                                                                                                                                                                                                the consensus between Midlands Connect, TfGM,
                     Worcester                                                                                                             Birmingham Airport Connectivity will create new                      Transport for the North and Network Rail is that
                                             Worcestershire

          Hereford
                     Great Malvern
                                                Parkway                                                                                    and more frequent links to Coventry and Birmingham                   many important network improvements can only be
                            Ledbury
                                                                                                                                           International, on the doorstep of Interchange HS2                    achieved if this major bottleneck is resolved.
                                                Cheltenham Spa                                                                             station, linking 2.2 million more people to the high
                                                                                                                                                                                                                                            Manchester
                                                                                                                                           speed network and Birmingham Airport. Derby,
                                                                                                                                           Sheffield, Newcastle, York, and Durham are among                                               Stockport
                                                                                                                                           the places that would benefit from these new direct
           Newport
Cardiff
                              Bristol Parkway
                                                                                                                                           rail connections, while Leamington, Solihull and
                      Bristol                                                                                                              Coventry would be among those benefitting from
                                                                                        Cllr George Duggins,                               enhanced local commuter links.
                                                                                        Leader of Coventry City Council
Midlands Engine Rail’s flagship scheme will create                                      “Infrastructure investment is central to our
space for 20 more trains every hour into and out                                        future success, which is why it’s so important
of Birmingham Moor Street station, improving                                            that Midlands Connect’s proposals are
                                                                                                                                                                                                                            Crewe
connections to the South West, Wales, and East                                          brought forward. This includes plans to
Midlands. As Birmingham Moor Street will be                                             reinstate direct rail connections between the
adjacent to the new high speed station at Curzon                                        cities of Coventry, Leicester and Nottingham
Street, the scheme will allow communities in Cardiff,                                   and the Birmingham Airport Connectivity
Bristol, Hereford and Worcester easy access to HS2,                                     scheme, which will open up rail access to
vastly enhancing its geographical reach.                                                Coventry and Birmingham International
                                                                                        stations for over two million people from
The Midlands Rail Hub will also drive huge benefits
                                                                                        Derby, Sheffield, Newcastle and beyond, as
for local commuters, reducing crowding and
                                                                                        well as boosting local commuter links.”
encouraging sustainable travel on a network that has
seen demand double over the past decade.                                                                                                                                                                                            Birmingham

   6                                                                                                                                                                                                                                                                7
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
Package East: Leveraging                                MC Conventional Compatible Services                     Accelerate Birmingham – Leeds                             The running of these faster services up to Leeds
                                                                                                                                                                          would occur alongside the commencement of high
                                                        Midlands Engine Rail includes plans for two HS2
Phase 2b Eastern Leg                                    conventional-compatible services that will run                                            Leeds
                                                                                                                                                                          speed services from a redeveloped London Euston
                                                                                                                                                                          station, currently scheduled for 2031.
(Incrementally delivered                                direct from: Bedford – Leicester – East Midlands
                                                        Hub – Leeds, and Nottingham – East Midlands Hub                                                                   This intervention would catalyse regeneration and
from 2027-2031)                                         – Birmingham. These services would run on both                                                                    development around the new HS2 station sites,
                                                        electrified and high speed tracks, and would join the                                                             generate operational income sooner and benefit
                                                        HS2 network at Toton via an alternative junction                                                                  communities in the East Midlands that have suffered
                                                        layout which allows direct connections onto the high                                                              from decades of underinvestment.
This package focuses on accelerating the                speed network in both directions.                                            Sheffield
commencement of high speed services to the
HS2 East Midlands Hub at Toton as well as the           This solution would bring HS2 trains directly into
                                                                                                                                                                             Lilian Greenwood,
economic centres of Chesterfield, Sheffield,            Nottingham and Leicester city centres, without the                         Chesterfield

                                                        need for interchange and more than halve current
                                                                                                                                                                             MP for Nottingham South
and Leeds, using HS2 as a catalyst for economic
                                                                                                                                                          East Midlands
development, regeneration and sorely-needed             journey times between economic centres in the                                                                        “The aim of the Integrated Rail Plan is to make
                                                                                                                                                           Hub (Toton)
regional transport improvements.                        Midlands and the North. Our proposal would see                                                                       the most of HS2; connecting more people into
                                                        journey times between Leicester and Leeds drop from                                                                  the high speed network. Not only can these
Access to Toton                                         120 to 50 minutes and Nottingham to Birmingham fall                                                                  plans bring high speed trains directly into
                                                        from 72 to 33 minutes.                                                                                               Nottingham and Leicester city centres, but
                                                                                                                                                                             they would more than halve current journey
                  East Midlands                                                Leeds
                                                                                                                                                                             times. It’s essential that Government provides
                  Hub (Toton)
                                                                                                                                                                             Midlands Connect with the resources it needs to
                                                                                                                                                                             bring them forward.”
        Derby                  Nottingham
                                                                                                                                                      To London
                                                                                                                    Birmingham
                               Loughborough
                      EMA                                                                                                                                                   Midland Main Line Electrification
                                                                                                                We believe that there could be an interim solution
                                                                                                                which would allow high speed services to run                The plans outlined in Package East require the
                                Leicester
                                                                                                                from Birmingham to the East Midlands Hub at                 full electrification of the Midland Main Line,
                                                                                                                Toton, Sheffield, Chesterfield and onto Leeds (via a        either to run (MC Conventional Compatible
                                                                      East Midlands             Nottingham      connection to the conventional rail network ten miles       services and Accelerate Birmingham – Leeds) or
This multimodal transport strategy is designed
                                                                      Hub (Toton)                               south of the city centre) as early as 2031, up to nine      to operate in a carbon efficient manner (Access
to support, accelerate and maximise the benefits
                                                                                                                years earlier than scheduled.                               to Toton). We ask that these vital plans are
of HS2 in the East Midlands by connecting towns,                                                Loughborough
                                                                                                                                                                            reinstated, and that Government commits to a
cities and villages across the region to the HS2 East                                                           This can be achieved by accelerating the construction
                                                                                                 Leicester                                                                  truly carbon-neutral rail network.
Midlands Hub at Toton. The rail interventions in                                                                of the Eastern Leg of Phase 2b from Birmingham
this plan include four shuttle services per hour from                                                           to the HS2 East Midlands Hub at Toton, all the way
                                                           Birmingham         Market Harborough
Derby, Leicester and Nottingham to the HS2 East                                                                 north to Crofton, just south of Leeds, as well as
Midlands Hub; plus reopening the Maid Marian Line                                          Kettering
                                                                                                                upgrading the conventional railway line between
to passenger traffic, connecting Mansfield to the HS2                                  Wellingborough
                                                                                                                Sheffield and Claydon.
East Midlands Hub. Phase One of the plan can be
                                                                                               Bedford          In the interim, these conventional compatible
delivered in the next decade.
                                                                                                                services would run from Birmingham to Crofton
                                                                                                                on the new high speed line, then run the remaining
   Cllr Kay Cutts MBE,                                                                                          ten miles from Crofton to Leeds on the existing
   Leader of Nottinghamshire County Council                                                                     network, terminating at two new platforms at Leeds
   “The arrival of High Speed Two in                    investment are spread far and wide. We are keen         station. This would be a temporary measure until the
   Nottinghamshire will bring with it widespread        to work alongside Government to ensure that the         logistically-complex approach to Leeds’ new high
   regeneration, development and highly-skilled         East Midlands sees benefits as soon as possible,        speed terminus is completed. However, these new
   jobs. This comprehensive plan ensures that           and that these improvements are included in its         platforms will provide much-needed capacity for
   communities in our towns and villages can access     Integrated Rail Plan”                                   additional commuter services into Leeds once the              CGI of planned HS2 East Midlands Hub at Toton, including
   these opportunities, and that the benefits of this                                                           full HS2 network is complete, the need for which is           on-site innovation campus and new housing development
                                                                                                                reinforced by Transport for the North.

  8                                                                                                                                                                                                                                9
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
Darren Henry,
                                                                                                                              MP for Broxtowe
Package Connect:                                         Birmingham – Black Country – Shrewsbury
                                                                                                                              “Levelling-up the UK economy means
Enhancing East – West                                          To Wales
                                                                                                                              spreading the benefits of Government
                                                                                                                              investment to all corners of the country. These
connectivity (Incrementally                                                           Wellington
                                                                                              Telford                         plans will create a truly green and connected
delivered from 2021-2033)                                          Shrewsbury
                                                                                      Wolverhampton
                                                                                                                              transport network for generations to come.
                                                                                                                              Our new high speed network will be a game-
                                                                                              Sandwell & Dudley               changer for the Midlands, we must now
                                                                                           Birmingham                         ensure it is fully integrated with Midlands
                                                                                                                                                                                                        Sir John Peace, Maria Machancoses, Robert Jenrick MP
This package includes the remaining elements of                                                                               Engine Rail.”
                                                                                                                                                                                                        and Lilian Greenwood MP at Midlands Engine Rail launch
Midlands Engine Rail that are focused on promoting
east – west connectivity across the Midlands region,     This scheme will increase the frequency of services
often on routes where the proportion of journeys         between Birmingham, the Black Country, Telford
made by rail is woefully low, or where poor service      and Shrewsbury, utilising the extra network capacity             What now?                                                              Our ‘asks’
levels are stifling additional demand. Many of these     freed up by HS2. This enhancement would also see
improvements utilise network capacity released by        the reintroduction of direct London – Telford services,          The Midlands Engine Rail programme and this                            That Midlands Connect is granted the
HS2 or have business cases that are strengthened         and link communities to the full high speed network              wider submission is the culmination of many                            opportunity to discuss its proposals with officials
by the increase in rail patronage our new high speed     via Birmingham Interchange station.                              years’ work, gathering in-depth evidence and                           in the Department for Transport and National
line will create.                                                                                                         building consensus amongst political, civic                            Infrastructure Commission
                                                         Nottingham – Lincoln
                                                                                                                          and business leaders from across the region.                           That Government provides the funding needed
Midlands Rail Hub
(Coventry-Leicester-Nottingham)                                                                                           Midlands Connect now seeks an open dialogue                            to bring forward the development of a number
                                                                                            Lincoln                       with the Department for Transport as it drafts                         of important, and time-sensitive projects, in-line
                            Nottingham                                                                                    its final Integrated Rail Plan.                                        with its ambitions to accelerate the delivery of
                                                                                                                                                                                                 infrastructure projects, as part of ‘project speed’
                                                                                       Newark Castle
                            Loughborough
                                                                                                                              Scheme                                      Development Stage                   Funding Required
                             Leicester
                                                                          Nottingham
                                                                                                                              Access to Toton (Phase                      Outline Business                    £4.5 million
                                                                                                                              One)                                        Case
                                                         We are currently investigating the potential for
                  Coventry                               line speed improvements, achieved through the
                                                         installation of an enhanced signalling system, and                   Birmingham Airport                          Full Business Case                  £20 million
The remaining improvement planned within our             additional services between Nottingham and Lincoln.                  Connectivity
Midlands Rail Hub scheme would reinstate direct
                                                         Derby – Stoke - Crewe
services between Coventry, Leicester and Nottingham
                                                                                                                              MC Conventional                             Outline Business                    £2 million
via a dive under at Nuneaton. The slow, indirect
                                                                                                                              Compatible services                         Case
service currently in place means that at present, only
                                                           Crewe
one per cent of journeys between these major cities
                                                                               Stoke-on-Trent                             Although not exhaustive, the ‘asks’ above relate to projects where the need for
are made by rail. This intervention will increase rail
mode share on this important route.                                                                               Derby
                                                                                                                          funding is most time sensitive.                                                     £26.5 million
      Cllr Ian Ward,
                                                                               Uttoxeter
                                                                                                                          Rail scheme development lifecycle
      Leader of Birmingham City Council                                                                                                                                            Strategic Outline
                                                                                                                                                                                                                              Outline Business Case
      “Midlands Connect’s technical experts have         Travellers on the Crewe-Derby rail corridor suffer                         Feasibility study                               Business Case
                                                                                                                                                                                                                                     (OBC)
      put these plans together using industry            from a slow, infrequent service. Midlands Connect is                                                                           (SOBC)
      insight, feedback from partners and crucially,     currently examining the case for higher line speeds
      evidence. Government should seriously              and more regular services – the latter is likely to
      consider these proposals as it writes its          be dependent on growth in demand linked to the                                                                                                                         Full Business Case
                                                                                                                                                                 Delivery
      Integrated Rail Plan.”                             opening of HS2 services at Crewe and at the HS2 East                                                                                                                         (FBC)
                                                         Midlands Hub

 10                                                                                                                                                                                                                                                        11
An Integrated Rail Plan for the Midlands - Accelerating, maximising and securing the benefits of HS2 Phase 2b - Midlands Connect
Immingham •
                                                                                                   • Grimsby

                                    •
                                    Glossop

                                           • Buxton      • Chesterfield              • Lincoln

                                                      • Matlock • Mansfield                             Skegness •
                                                                              • Newark-On-Trent
                           • Stoke-On-Trent
                                                                                                 Boston •
                                                                  • Nottingham
                                                        • Derby                    • Grantham
• Oswestry
                              • Stafford        • Burton upon Trent
                                                            • Loughborough
         • Shrewsbury
                  • Telford           • Lichfield                                • Oakham
                                           • Tamworth              • Leicester
             Wolverhampton • • Walsall
                                        Nuneaton •
                     Dudley • • Oldbury
                                    • Birmingham
          Kidderminster •      Solihull •       • Coventry
          • Ludlow
                                   • Redditch
                                   Warwick •
               Worcester •       Stratford- •
                                 Upon-Avon

         • Hereford

             • Ross -On-Wye

     Baskerville
               House, 2 Centenary Square, Birmingham, B1 2ND