799 Adopted Minutes Water, Waste and Energy Committee Meeting - Wednesday 3 March 2021
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
799 Adopted Minutes for the Water, Waste and Energy Committee Meeting to be held Wednesday 3 March 2021 at 9 am City of Gold Coast Council Chambers 135 Bundall Road Surfers Paradise
799th Council Meeting 9 March 2021 2 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes Index 799 Adopted Minutes Water, Waste and Energy Committee Meeting Wednesday 3 March 2021 PRESENTATIONS: - Kerbside Collection Area Expansion – Review Update - Confidential Item Direct. File Page Subject 1 WW LG115/1377/01/2020(P1) 4 Confirmation of Minutes 2 WW LG115/1377/01/2020(P1) 13 Conflict of Interest Declarations 3 WW CM787/790/06/01(P1) 15 Water, Waste and Energy Committee Action List and Forward Planning Schedule 4 WW WSS1125/1227/02(P1) 18 Water and Waste Annual Register of Council Directions 5 WW FN334/252/21(P1) 20 Water and Sewerage Services Monthly Financial Report for the month of January 2021 6 WW FN334/252/20(P6) 40 Waste Services Monthly Financial Report for the month of January 2021 7 WW FN334/252/21(P1) 52 Energy Management Unit Monthly Financial Report for the month of January 2021 8 WW WSS382/343/08(P1) 58 Inflow Mitigation: Approved Inspection Program for Private Sewerage Plumbing Closed Session 9 WW WSS1115/343/02 72 Northern Gold Coast Recycled Water Scheme KEY: OCEO - Office of the Chief Executive Officer OCOO Office of the Chief Operating Officer EPE - Economy, Planning and Environment OS - Organisational Services LC - Lifestyle and Community TI - Transport and Infrastructure WW - Water and Waste
799th Council Meeting 9 March 2021 3 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ADOPTION BY COUNCIL 9 MARCH 2021 RESOLUTION G21.0309.015 moved Cr Hammel seconded Cr PJ Young That the Minutes of the Water, Waste and Energy Committee Meeting of Wednesday 3 March 2021, covered by Recommendations numbered WWE21.0303.001 to WWE21.0303.008 (Item 9), be adopted. CARRIED UNANIMOUSLY Cr Hammel voted in the positive ATTENDANCE Cr G O’Neill (Chairperson) Cr M Hammel Cr PJ Young Cr R Bayldon-Lumsden Cr R La Castra Cr G Tozer Cr D McDonald Cr W Owen-Jones Visiting Councillor Cr B Patterson Visiting Councillor Cr PC Young Visiting Councillor Mr P Heaton Director Water and Waste Mr R Packer Manager Strategy and Innovation Mr C Truscott Manager Asset Solutions APOLOGY / LEAVE OF ABSENCE Nil PRESENTATIONS Kerbside Collection Area Expansion – Review Update - Confidential Mr Rod Packer
799th Council Meeting 9 March 2021 4 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 1 WATER AND WASTE CONFIRMATION OF MINUTES LG115/1377/01/2020(P1) That the minutes of the Seven Hundred and Ninety Eighth Water, Waste and Energy Committee Meeting held on Wednesday 10 February 2021 be confirmed. COMMITTEE RECOMMENDATION WWE21.0303.001 moved Cr Tozer seconded Cr Hammel CARRIED
799th Council Meeting 9 March 2021 5 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes Attachment 1.1
799th Council Meeting 9 March 2021 6 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 7 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 8 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 9 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 10 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 11 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 12 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes
799th Council Meeting 9 March 2021 13 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 2 WATER AND WASTE CONFLICT OF INTEREST DECLARATIONS LG115/1377/01/2020(P1) Declarable Conflict of Interest – During Meeting Councillor Name Cr Hammel Matter Description Northern Gold Coast Recycled Water Scheme Meeting Name Council Meeting Meeting Date 9 March 2021 Item Number 9 Item Reference Pursuant to section 150EQ(2) of the Local Government Act 2009, I hereby provide notice that I have a declarable conflict of interest in this matter, the nature and particulars of which are as follows: Nature of the declarable conflict of interest I own property in the vicinity. If the declarable conflict of interest arises because of the councillor’s relationship with a related party The name of the related party Cr Mark Hammel The nature of the relationship of the related party to the councillor The nature of the related party’s interests in the matter Owner of property in the vicinity If the councillor’s or related party’s personal interests arise because of the receipt of a gift or loan from another person The name of the other person The nature of the relationship of the other person to the councillor or related party The nature of the other person’s interests in the matter The value of the gift or loan, and the date the gift was given or loan was made I am voluntarily deciding not to participate in making a decision about the matter. I am seeking permission to participate in making a decision about the matter.
799th Council Meeting 9 March 2021 14 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 2 WATER AND WASTE CONFLICT OF INTEREST DECLARATIONS LG115/1377/01/2020(P1) The reasons why my participation would improve decision making in the public interest are as follows: I own property in the vicinity however my property is not part of this report. PROCEDURAL MOTION moved Cr Tozer seconded Cr O’Neill Pursuant to section 150ES(3)(a) of the Local Government Act 2009, Council resolves that: Cr Hammel may participate in the decision despite the Councillor’s conflict of A interest because he has no greater personal interest in the matter than that of other persons in the local government area CARRIED Cr Hammel did not vote.
799th Council Meeting 9 March 2021 15 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 3 WATER AND WASTE WATER, WASTE AND ENERGY COMMITTEE ACTION LIST AND FORWARD PLANNING SCHEDULE CM787/788/06/01(P1) Proposed Date Subject Action Officers Action March 2021 Coomera Shores Water and Christian Sewerage Services Truscott/ Mark Johnson March 2021 Review of Kerbside Bin Service Area Sam Atkinson/ That a review of the kerbside bin service area particularly Rod Packer focusing on unserviced rural residential lots outside of the Petition – Extension of Waste declared waste collection area be completed and brought Collection Service in Mudgeeraba back to a future committee meeting. (response will be included in “Review of Kerbside Bin Service Area” Agenda Petition submitted to 789 Council meeting held 27 May Item) 2020. Resolution: G20.0527.035.0527.035 That the above Petition be received and referred to the appropriate committee for consideration and report to Council. March 2021 Waste Management Land Kathy Baker That a report comes back to Council on this matter by March Requirements 2021. Committee Recommendation: WWE20.0722.0076
799th Council Meeting 9 March 2021 16 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 3 WATER AND WASTE WATER, WASTE AND ENERGY COMMITTEE ACTION LIST AND FORWARD PLANNING SCHEDULE CM787/788/06/01(P1) Proposed Date Subject Action Officers Action TBC Waste and Recycling Centres Mairead Network Operations (operations and Lenihan / access) Rod Packer Council Resolution: G19.0730.023 May 2021 Inflow Mitigation: Approved Inspection Dominique Package 3 update Program for Private Sewerage Keirens / Jay Plumbing San Juan June 2021 Hope Island Water Metering Review Chris Owen That Water and Waste prepare an agenda item detailing feasibility and implications alternate water meter reading and water meter asset custodianship options and associated recommendations for Hope Island Body Corporate areas, and implications for similar schemes. Further report as agreed at Committee (Item 10 General Business 18 Nov 2020) RECOMMENDATION It is recommended that Council resolve as follows: That the Action List and Forward Planning Schedule for Water, Waste and Energy Committee be noted. Authorised by: Paul Heaton iSPOT#75297798 Director Water and Waste
799th Council Meeting 9 March 2021 17 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 3 (Continued) WATER AND WASTE WATER, WASTE AND ENERGY COMMITTEE ACTION LIST AND FORWARD PLANNING SCHEDULE CM787/788/06/01(P1) COMMITTEE RECOMMENDATION WWE21.0303.002 moved Cr Tozer seconded Cr PJ Young That the Action List and Forward Planning Schedule for Water, Waste and Energy Committee be noted. CARRIED
799th Council Meeting 9 March 2021 18 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 4 WATER AND WASTE WATER AND WASTE ANNUAL REGISTER OF COUNCIL DIRECTIONS WSS1125/1227/02(P1) STANDING AGENDA ITEM: Committee Recommendation: WS14.0430.007 / Council Resolution: G14.0506.025 “That Gold Coast Water establish a standing item on the Water Services Committee Agenda which is a register (and thus an agreed record) of any “directions” that Council gives Gold Coast Water for reporting in the annual operations report.” That is: - a resolution that goes against or substantially modifies the recommendations of the Officers and; - has a (or potential to have a) material/commercial impact on the business unit. Council Council Description 2019-20 2020-21 Meeting Resolution That the adopted infrastructure charges are adjusted so that there is a 100% discount for family accommodation dwellings of 100m2 GFA or less for any approvals issued on or after 1 July 2014 through the remainder of this Council’s term. Permanent changes to Adopted Infrastructure Charges Resolution (AICR): 1. Existing building: no infrastructure charges levied for any change in non- residential land use (ongoing). 2. Expansion: for non-residential land uses, up to an additional 50 per cent of GFA or a maximum of 500m², whichever is the lower, will be exempt from infrastructure charges (ongoing). 3. Family accommodation: no charge for family accommodation dwellings of 100m² GFA or less. Family accommodation dwellings greater than 100m² GFA will be charged at 40 per cent of the relevant AICR charge (ongoing). 771 G19.0326.022 4. Not-for-profit community groups: rebates for the water and wastewater networks will be restored, following the return of responsibility to the City Nil Rebates (ongoing). Recommendation: WW19.0321.002
799th Council Meeting 9 March 2021 19 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 4 (Continued) WATER AND WASTE ANNUAL REGISTER OF COUNCIL DIRECTIONS WSS1125/1227/02(P1) RECOMMENDATION It is recommended that Council resolve as follows: That the Water and Waste Annual Register of Council Directions be noted. Authorised by: Paul Heaton iSPOT#43956542 Director Water and Waste COMMITTEE RECOMMENDATION WWE21.0210.003 moved Cr Tozer seconded Cr PJ Young That the Water and Waste Annual Register of Council Directions be noted. CARRIED
799th Council Meeting 9 March 2021 20 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 WATER AND WASTE WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Attachment 1: Detailed Income Statement 1 BASIS FOR CONFIDENTIALITY Not Applicable. 2 EXECUTIVE SUMMARY Not Applicable. 3 PURPOSE OF REPORT This report presents the Water, Waste and Energy Committee with the Water and Sewerage Services 2020-21 financial performance as at 31 January 2021. Comparisons are against Council’s 2020-21 September revised budget. 4 PREVIOUS RESOLUTIONS Not Applicable. 5 DISCUSSION 5.1 High Level Financial Summary Year to Date Full Year Water & Sewerage Services Financial Summary Actual Revised Initial Revised Budget Budget Budget Var Var 31 January 2021 ($M) ($M) ($M) % ($M) ($M) Operating Revenue 314.81 311.56 3.25 1.0% 536.15 533.33 Flow-Dependent Expenditure 126.81 127.15 0.34 0.3% 210.79 210.80 Operating Revenue net of Flow Dependent Expenditure 188.00 184.41 3.59 1.9% 325.36 322.53 Gross Margin 0.63 0.63 0.65 0.65 Total Controllable Operating 66.17 70.94 4.77 6.7% 120.42 123.24 Expenditure Loss on Sale of Assets 0.31 2.22 1.91 85.9% 5.00 5.00 Net Profit before Capital Revenue 121.52 111.25 10.27 9.2% 199.94 194.29 Total Capital Revenue 36.17 33.75 2.42 7.2% 65.00 65.00 EBITDA 157.69 145.00 12.69 8.8% 264.94 259.29 Table 1 – Water and Sewerage Services - Year to Date Financial Summary Table 1 presents the financial position for Water and Sewerage Services as at 31 January as 8.8% or $12.69 million above forecast. This is predominantly the result of total controllable operating expenditure being $4.77 million (6.7%) below forecast, operating revenue being $3.25 million (1.0%) above forecast and capital revenue being $2.42 million (7.2%) above forecast.
799th Council Meeting 9 March 2021 21 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Major variances will be discussed in the following paragraphs with a detailed Income Statement contained in Attachment 5.1 to the report. 5.2 Operating Revenue ($3.25 million Favourable) 5.2.1 Rates Revenue Financial Summary ($3.17 million Favourable) Year to Date Full Year Water & Sewerage Rates Actual Revised Initial Revised Budget Budget Budget Revenue Var Var 31 January 2021 ($M) ($M) ($M) % ($M) ($M) Access Charges Water 41.33 41.51 (0.18) (0.4%) 71.23 71.23 Sewage 108.18 108.50 (0.32) (0.3%) 187.71 187.71 Total Access Charges 149.51 150.01 (0.50) (0.3%) 258.94 258.94 Usage Charges Revenue Water - gross 139.30 137.22 2.08 1.5% 226.80 226.55 Sewage - gross 20.82 19.52 1.30 6.6% 39.98 39.84 Non Drinking Water 0.94 0.80 0.14 18.1% 1.21 1.21 Less: Concealed Leakage (1.08) (1.23) 0.15 12.4% (2.50) (2.11) Total Usage Charges Revenue 159.98 156.31 3.67 2.3% 265.49 265.49 Total Rates Revenue 309.49 306.32 3.17 1.0% 524.43 524.43 Table 2 – Water and Sewer Rates Revenue Forecast Utility Rates revenue is $3.17 million (1.0%) ahead of forecast, with access charges being $0.50 million (0.3%) below forecast and usage charges revenue being $3.67 million (2.3%) above forecast. Access Charges § Year-to-date water access charges revenue recorded is $0.18 million (0.4%) below forecast. Total water service connections at 31 January 2021 are 269,618 representing an increase of 0.87% in connections since 30 June 2020. § Year-to-date sewerage access charges revenue recorded is $0.32 million (0.3%) below forecast. Total sewerage service connections at 31 January 2021 are 255,615 representing an increase of 0.91% in connections since 30 June 2020. Total forecast growth for the 2020-21 financial year is 2.26% for both water and sewerage connections, with actual connections growth tracking slightly below forecast as at 31 January 2021. Access charges will be closely monitored, and necessary amendments will be made at the March 2021 budget review, if required.
799th Council Meeting 9 March 2021 22 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Usage Charges Revenue Total Usage Charges revenue is recorded at $3.67 million (2.3%) above forecast as at 31 January 2021. • Year-to-date water usage revenue is above forecast by $2.08 million (1.5%). The increase in usage revenue is explained by the increase in demand for the year, as outlined in Section 5.3 below. • Year-to-date sewage volumetric revenue is above forecast by $1.30 million (6.6%). This is the result of the conservative usage estimates adopted for the budget, taking into account the expected bounce back from COVID-19 shutdowns for non-residential customers which has tracked ahead of initial expectations. Usage charges will be closely monitored, and necessary amendments will be made at the March budget review, if required. 5.2.2 Other Operating Revenue ($0.08 million Favourable) Other operating revenue is $0.08 million (1.3%) above forecast due to: • $0.16 million for increased revenue from landfill leachate treatment. • $0.08 million due to increased demand for laboratory testing within Water and Waste. • $0.25 million unfavourable due to reduced rental revenue from a recently acquired strategic property purchase. Income is not expected to be received until next financial year. Other operating revenue will be closely monitored, and necessary amendments will be made at the March budget review, if required. 5.3 Flow Dependent Expenditure ($0.34 million Favourable) Flow dependent expenditure is within 1% of the revised budget. Bulk Water Purchases ($1.18 million Unfavourable) Bulk water purchases for the month of January 2021 were below forecast by 935 ML (14.8%) but are 460 ML (1.3%) above forecast on a year to date basis. The demand forecast used for the initial budget was based on drought conditions for the full financial year. As outlined in Graph 1, the South East Queensland adaptive drought response identifies that when combined dam levels reach 60% voluntary water restrictions come into effect, with formal restrictions when dam levels reach 50%. As at the end of January, the combined dam levels were 57.3%. As formal water restrictions have not come into effect, it has led to an increase in bulk water purchases, with the cost offset by an increase in usage revenue.
799th Council Meeting 9 March 2021 23 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Graph 1 South East Queensland adaptive drought response approach Rainfall for January was 83% of the long-term average, with 114 mm recorded at the Gold Coast Seaway. Financial year-to-date rainfall is 119% of the long-term average with 725 mm recorded at the Gold Coast Seaway. Graph 2 compares water supplied versus the demand forecast adopted for the revised budget. Rainfall recorded for the month is also incorporated. Water demand will be closely monitored and will be adjusted at the March budget review, if required. If an adjustment is required, then this will also flow through to water and sewage usage revenue.
799th Council Meeting 9 March 2021 24 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Graph 2 - Analysis of Water Supplied versus Demand Forecast Electricity ($1.08 million Favourable) Electricity expenses are $1.08 million or 14.8% below forecast as a result of lower flows into Coombabah STP from the Surfers/Broadbeach area in the first couple of months of the financial year (now recovered to normal flows). In addition, the administrative mark-up paid to the Energy Management Unit reduced for large sites which wasn’t recognised in the initial budget. A budget reduction will be proposed as part of the March budget review.
799th Council Meeting 9 March 2021 25 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.4 Controllable Expenditure ($4.77 million Favourable) At a whole of business unit level Controllable Expenses are $4.77 million (6.7%) below forecast. Major contributing factors to this variance are discussed below. Consultants ($1.69 million Favourable) Consultants are $1.69 million or 48.7% below forecast mainly due to lower than forecast expenditure in the following: • Water and Sewerage Services Infrastructure Plan (WSSIP) Detailed Planning: this project is tracking behind forecast due to reprioritisation of resources to meet higher priority projects. • Elanora Environmental Investigation: Delays in the ecology field work, sediment and water sampling due to wet weather events has resulted in the lower than forecast expenditure. In addition, project works are adaptive based on the Environmental Regulator’s requirements. These works will carry over into 2021-22. • Planning Investigations: this project is tracking behind forecast as the scope is identified reactively, with less works required than initially expected. A budget adjustment will be requested as part of the March budget review. • STP Planning Program: this project is tracking behind forecast due to reprioritisation of resources to meet higher priority projects. Materials and Services ($1.50 million Favourable) Materials and services are $1.50 million or 7.9% below forecast due to: • Water Assist Program: an allocation was provided for as part of the COVID-19 Community Assistance Package, there have been delays in finalising the structure and the program will be available to customers in the second half of the financial year. • Gravity Sewer Condition Assessment: this project is tracking below forecast due to ongoing issues with poor quality of data from the contractor. As a result, progress claims have been put on hold until the data quality issue is resolved. This is partially offset by: • Higher than forecast expenditure on major contract implementation. • Increased maintenance costs at the sewage treatment plants due to an increase in reactive maintenance required on mechanical and electrical equipment at the plants.
799th Council Meeting 9 March 2021 26 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Employee Expenses ($1.48 million Favourable) Employee expenses are $1.48 million (4.9%) below forecast due to a combination of: • Delays in finalising contracts has resulted in delays the recruitment process for resources for the Utility Billing Solution Stabilisation project. • Identification of several positions that split their time between tactical asset management and capital project delivery has led to a decrease in operational employee expenses, with the balance of the cost being picked up in capital projects and capitalised at project completion. Employee expenses will be closely monitored, and necessary amendments will be made at the March budget review, if required. Sewage Treatment Charge ($0.55 million Favourable) An allowance of $0.4 million was provided for exceeding effluent quality and volume limits for treatment of sewage at the Beenleigh STP as part of the Service Level Agreement with Logan City Council. To date over limit charges incurred have been very minimal. 5.5 Loss on Asset Disposal ($1.91 million Favourable) Processing of assets for 2020-21 commenced in October. It is expected processing shall ramp up in the coming months to align with the asset revaluation exercise. 5.6 Capital Revenue ($2.42 million Favourable) Developer (cash) contributions are $6.92 million (33.9%) above forecast. Developer contributions are dependent on the level of development activity across the City which fluctuates both across financial years and during the year. An adjustment to developer contributions was made as part of the December budget review. Further monitoring will occur, and necessary adjustment will be made at the March budget review, if required. Contributed assets are $4.50 million (33.7%) below forecast. Processing of assets commenced in October following completion of the 2019-20 financial year activities and processing will increase over the second half of the financial year. Similar to developer contributions, contributed assets are dependent on the level of development activity across the City which fluctuates over the year.
799th Council Meeting 9 March 2021 27 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.7 Community Returns Income Tax ($3.99 million Unfavourable) Water and Sewerage Services is a commercialised business unit subject to the Local Government Taxation Equivalents Regime (LGTER). As part of this regime, a Pay As You Go (PAYG) Instalment Activity Statement must be prepared and submitted on a monthly basis, with payment of a PAYG instalment to Council. The current instalment rate as issued by our tax assessors is 6.86%. The instalment rate is applied to total revenue generated to derive the amount of PAYG tax payable each month. At year end, a final taxation return will be prepared, based upon taxable income, and utilising the company taxation rate of 30% to calculate total taxation payable for the year. Relevant adjustments will be made to record this annual tax liability to Council. 5.8 Capital Program 5.8.1 Capital Expenditure The Water and Sewerage Services revised capital program consists of 82 projects totalling $165.99 million. Water and Sewerage Services Capital Expenditure as at 31 January 2021 Year to Date Full Year Actual Revised Budget Initial Revised Forecast Q1 Variance Variance Product Expenditure Q1 Budget ($M) ($M) % ($M) ($M) ($M) Sewerage 63.39 71.36 (7.97) (11%) 146.93 147.85 Water 11.57 12.10 (0.53) (4%) 18.78 17.87 Corporate 0.19 0.23 (0.04) (17%) 0.27 0.27 Total Capital 75.15 83.68 (8.54) (10%) 165.99 165.99 Table 3 – Capital Expenditure ($‘000’s) Year to date capital expenditure of $75.15 million represents a variance of 10% below the year to date revised forecast of $83.68 million.
799th Council Meeting 9 March 2021 28 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Product Variances Sewerage The sewerage program is $7.97million (11%) below forecast. The following projects are the main contributors to this variance: • Coombabah STP Stage 6 Upgrade: $4.28 million below forecast. Project expenditure is continuing to track behind forecast due to wet weather events experienced in December. Further delays related to receipt of detailed designs has slowed construction activities on site. Despite these delays, it is anticipated budget will be fully expended this financial year. • SPS Wet Well Relining 2019-20: $0.55 million below forecast. Project expenditure is tracking behind forecast as the maintenance hole refurbishment contract was not able to be extended beyond November 2020, leaving no delivery mechanism for these works. As a result, a significant budget reduction will be proposed as part of the March budget review. • Long Term Recycled Water Release Stage 1: $0.96 million below forecast. Project expenditure is tracking behind forecast as the earlier notice from the contractor for a latent claim related to the cracked tunnel pipes was formally withdrawn. • SPS CO13 Vacuum Upgrade: $0.39 million below forecast. The project has been delayed due to COVID-19 related supply chain issues relating to the delivery of the vacuum generators, discharge pumps, switchboard and separators. It is still anticipated that the project scope will be fully delivered by 30 June 2021. • Sewer Pressure Main Renewals: $0.71 million below forecast. Construction synergies with the recycled water network expansion project have impacted the delivery of project scope this financial year. Works have been deferred to 2021-22. A budget reduction will be proposed as part of the March budget review. • Infiltration Reduction Pilot Trial: $0.31 million below forecast. This project has been delayed due to the rescheduling of the CCTV assessment from December 2020 to March 2021 due to significant wet weather events. These works are only able to be undertaken during high tide and can be severely impacted by wet weather. The project aims to be completed by 30 June 2021. Water The water program is $0.53 million (4%) below forecast. The following project is the main contributor to this variance: • WPS BU1 Upgrade: $0.40 million below forecast Project expenditure is tracking behind forecast due to wet weather experienced during December 2020. Redesign of pipework connections and subsequent lead time for procurement of the required pipe and fittings has led to further delays. Notwithstanding this, the project is expected to be completed by 30 June 2021.
799th Council Meeting 9 March 2021 29 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.8.2 Status Update – Major Investments Coombabah Sewage Treatment Plant Stage 6 Upgrade Project scope and budget This project involves the upgrade of Coombabah Sewage Treatment Plant, (STP), to provide additional treatment capacity to cater for growth and to meet licence requirements. The preferred Stage 6 option involves an augmentation to approximately 120,000 Equivalent Person (EP) utilising existing biological nutrient removal technology. This includes a new Preliminary Treatment Facility (PTF), new bioreactor and associated clarifiers, disinfection system, waste sludge thickening and dewatering and associated ancillary and support facilities. The revised budget for 2020-21 is $68.12 million. Achievements for January • Contract works progressing as per the contractor's program. • Design development progressing and is now on critical path. • Contaminated soil testing program complete with Management Plan under development. • Driven concrete piling commenced. Major issues No major issues. Financial Performance Year to Date Whole Project Forecast ($) 32,345,231 Budget ($) 155,038,820 Expenditure ($) 28,063,661 ITD Expenditure ($) 33,981,231 Variance ($) (4,281,570) Remaining ($) 121,057,589 Variance (%) (13%) Remaining (%) 78%
799th Council Meeting 9 March 2021 30 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Long Term Recycled Water Release Stage 1 Project scope and budget The City’s existing excess recycled water release system at the Seaway is nearing capacity. The Long Term Recycled Water Release Plan aims to provide a city wide solution to cater for excess recycled water to support continued growth and economic development of the City. Stage 1 consists of infrastructure upgrades that increase capacity and allow incremental staging of the ultimate solution to cater for both average and peak recycled water release for the whole of the City. Forecast completion is April 2021. The revised budget for 2020-21 is $18.0 million. Achievements for January • The possible latent condition claim, in relation to the cause of the cracked tunnel pipes, has been formally withdrawn. • Completed stripping of internal equipment from the tunnel. • Commenced demobilisation – overhead gantry crane, separation equipment and ancillary equipment removed from site. • Commenced preparations for testing and final connections. Major issues No major issues. Financial Performance Year to Date Whole Project Forecast ($) 14,894,622 Budget ($) 100,355,770 Expenditure ($) 13,935,649 ITD Expenditure ($) 96,291,419 Variance ($) (958,973) Remaining ($) 4,064,351 Variance (%) (6%) Remaining (%) 4%
799th Council Meeting 9 March 2021 31 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Recycled Water Network Expansion Stage 1 Project scope and budget Infrastructure works required for the expansion of the recycled water network to implement improved utilisation of recycled water across the City thus reducing ultimate ocean outflows. The cost of this infrastructure will be recovered in recycled water customer pricing. The revised budget for 2020-21 is $7.5 million. Achievements for January • Select tender assessments completed. • Deviation / clarification responses 95% complete. Major issues No major issues. Financial Performance Year to Date Whole Project Forecast ($) 1,483,117 Budget ($) 21,466,874 Expenditure ($) 815,009 ITD Expenditure ($) 3,856,883 Variance ($) (668,108) Remaining ($) 17,609,991 Variance (%) (45%) Remaining (%) 82%
799th Council Meeting 9 March 2021 32 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Long Term Recycled Water Release Elanora Project scope and budget The City’s existing excess recycled water release system at the Seaway is nearing capacity. The Long Term Recycled Water Release Plan aims to provide a city wide solution to cater for excess recycled water to support continued growth and economic development of the City. The Elanora component consists of pump station and pipeline upgrades from the Elanora Sewage Treatment Plant. The revised budget for 2020-21 is $9.35 million. Achievements for January • Continuing with building repairs and modification works to the Recycled Water Booster Pump Station building at Elanora. • Concrete crack repair carried out in Recycled Water Booster Pump Station building at Elanora. • Blockwork construction for the main building at Cassowary Drive. • Concrete pour for the suspended roof slab for the electrical room at Cassowary Drive. • Pouring of the concrete slab for the above ground pipework and dismantling and re- erection of the sampling shed at Merrimac. Major issues • Delays experienced in receiving the electrical design package from the contractor. Financial Performance Year to Date Whole Project Forecast ($) 3,239,786 Budget ($) 13,914,979 Expenditure ($) 3,188,884 ITD Expenditure ($) 4,253,863 Variance ($) (50,902) Remaining ($) 9,661,116 Variance (%) (2%) Remaining (%) 69%
799th Council Meeting 9 March 2021 33 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Pimpama STP Stage 2 Works Project scope and budget This project involves the construction of the Pimpama Sewage Treatment Plant Stage 2 works to accommodate for an additional 71,300 Equivalent Person (EP) growth in the Pimpama Catchment and diverted Stapylton Catchment area as identified through the LGIP process. The major elements of the recommended Stage 2 upgrade includes; inlet works expansion, full phosphorus and nitrogen removal (Biological Nutrient Removal), activated sludge process, sludge handling upgrade, tertiary treatment to maintain existing water quality and recycled water pump station upgrade. The revised budget for 2020-21 is $1.64 million. The project remains on hold as negotiations continue with Logan City Council to continue to transfer the Stapylton load to Loganholme STP. Achievements for January • A minor Scope of Works has been developed to mitigate potential impacts of the delay of the major Stage 2 Upgrade. Major issues No major issues. Financial Performance Year to Date Whole Project Forecast ($) 57,124 Budget ($) 89,397,299 Expenditure ($) 67,090 ITD Expenditure ($) 2,139,389 Variance ($) 9,966 Remaining ($) 87,257,910 Variance (%) 17% Remaining (%) 98%
799th Council Meeting 9 March 2021 34 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.9 Other Financial Activities 5.9.1 Community Service Obligations In accordance with Sections 23 and 24 of the Local Government Regulation 2012: …The cost of carrying out community service obligations, less any revenue received from performing the obligations must be treated as revenue for the significant business activity. {Section 23} (and) …A community service obligation is an obligation the local government imposes on a business entity to do something that is not in the commercial interests of the business entity to do. 5.9.1.1 Community Service Obligations – Catchment Management Unit Catchment Management Unit protects human health in recreational waters by monitoring the state of the City’s water environments and providing rapid reporting of the health status of primary contact recreation areas. It supports the maintenance of legislated environmental values in the City’s water environments through catchment planning and the implementation of appropriate environmental restoration actions. Catchment Management activities are funded by a combination of a Community Service Obligation (CSO) and the Water and Sewerage Services’ general operating budget. At adoption of Council’s initial budget, the total value of the CSO is $2,042,705 comprising “Catchment Activities” and “SLA for Corporate Services”, as shown in Table 4. This value remains unchanged following the adoption of the September budget review. The remaining activities outlined in Table 4 are those funded from the Water and Sewerage Services’ general operating budget. CSO Catchment Management activities are progressing in line with expectations. Water and Sewerage funded activities are below forecast with expenditure to ramp up during the remaining half of the year. Initial Revised YTD Catchment Management Unit - Spent Budget Budget Actuals Operational (%) ($'000s) ($'000s) ($'000s) Catchment Activities 1,594 1,594 906 56.8% SLA for Corporate Services 448 448 262 58.3% Subtotal CSO Funded 2,043 2,043 1,168 57.2% CMU Operations 400 516 178 34.6% Healthy Waterways Contribution 321 121 0 0.0% WaterSafe Monitoring & Investigations 150 250 28 11.3% Laboratory Testing Services 550 450 230 51.1% Community Action Support 220 220 206 93.5% Subtotal Water and Sewerage Funded 1,641 1,557 642 41.3% Total 3,683 3,599 1,810 50.3% Table 4 – Catchment Management Unit ($‘000’s)
799th Council Meeting 9 March 2021 35 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.9.1.2 Community Service Obligations – Infrastructure Charges Waivers Detailed information is not currently available with regard to the permanent discounting of infrastructure charges for “existing buildings”, “expansion” and “family accommodation” development applications. For the 2020-21 year to date, no foregone revenue in the form of waived infrastructure charges under the City’s Non-Profit Community Group Rebate system has been identified. 5.9.2 Water and Sewage Leakage Relief The objective of this policy is to ensure uniform and transparent application of relief from water usage charges and sewage volumetric charges in cases of proven concealed leakage. Revenue Services administers the Policy on behalf of the City. Table 5 provides summary level detail of the leakage remissions approved up to 31 January 2021. A total of 74 concealed leak applications were received in January 2021 with 42 receiving approval, and paid remissions totalling $0.026 million. For the year to date, there are eleven remissions greater than $10,000 which total $0.35 million or 32.5% of total remissions. Details of remissions are provided separately to Councillors. The budget for concealed leakage remissions has been reduced from $2.50 million in the Initial Budget to $2.11 million in the September budget review. Remissions paid to January are 12.4% below the revised budget. Water Sewer Total Number Average Total Leak Remission Remission Remission Month of Loss per Volume (kl) Value Value Value Approvals Account (kl) ($'000) ($'000) ($'000) Jul-20 205 63,891 312 119 10 129 Aug-20 261 74,966 287 136 37 173 Sep-20 360 176,380 490 199 130 328 Oct-20 253 82,759 327 134 81 215 Nov-20 98 52,732 538 39 153 192 Dec-20 29 6,493 224 12 4 16 Jan-21 42 10,566 252 24 1 26 Total 1,248 467,787 375 663 415 1,078 Budget provided for year 1,499 611 2,110 Proportion of budget approved to date 44.2% 68.0% 51.1% Table 5 – Summary of Concealed Leakage Remissions
799th Council Meeting 9 March 2021 36 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) Table 6 illustrates that 87.3% of applications approved to date relate to residential customers, representing 47.0% of the value of remissions provided. Customer Type Approvals Total Leak Value of Remissions Provided Volume Water Sewer Total # % % (kl) ($'000) ($'000) ($'000) Residential Customers Owner Occupied premises 775 62.1% 202,612 367 4 371 34.4% Rental/Tourist Rental premises 314 25.2% 84,769 107 29 136 12.6% Total Residential Customers 1,089 87.3% 287,381 474 34 507 47.0% Non-Residential Customers 159 12.7% 180,406 189 382 571 53.0% 1,248 100.0% 467,787 663 415 1,078 100.0% Proportion of Total Remissions 61.5% 38.5% Table 6 – Summary of Concealed Leakage Remissions by Customer Type and Product Graph 2, depicts the value of remissions provided over the past four years, compared to the value provided to date for 2020-21. The 2019-20 year represents the first year of rolling billing however there were five usage periods billed as part of the transition. As previously communicated to Council, the policy is due for renewal and will be implemented in the 2021 calendar year. Graph 2 – Concealed Leakage Remissions Paid
799th Council Meeting 9 March 2021 37 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 5.10 Future Budgetary Trends There are no major future budgetary trends. 6 ALIGNMENT TO THE CORPORATE PLAN, CORPORATE STRATEGIES AND OPERATIONAL PLAN Not Applicable. 7 FUNDING AND RESOURCING REQUIREMENTS Not Applicable. 8 RISK MANAGEMENT The following risk assessment applies to this report: Risk Number Description Risk No. Failure to achieve a sustainable long term financial position leading CO000435 to negative impacts on Council’s ability to deliver on its key focus area commitments. 9 STATUTORY MATTERS Not Applicable. 10 COUNCIL POLICIES The following policies have been taken into account when preparing this report: § Gold Coast Water Capital Structure and Community Returns Policy. § Revenue Policy. § City of Gold Coast Budget Review Policy. § Water and Sewage Leakage Relief Policy. 11 DELEGATIONS Not Applicable.
799th Council Meeting 9 March 2021 38 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 5 (Continued) WATER AND SEWERAGE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/21(P1) 12 COORDINATION AND CONSULTATION Name and/or Title of the Directorate or Is the Stakeholder Satisfied Stakeholder Consulted Organisation With Content of Report and Recommendations (Yes/No) (comment as appropriate) Tanya Cooper Office of the OCOO Yes Management Accountant 13 STAKEHOLDER IMPACTS Not Applicable. 14 TIMING Not Applicable. 15 CONCLUSION Water and Sewerage Services Earnings Before Interest and Tax (EBIT) for the period to 31 January 2021 is 8.8% or $12.69 million above forecast. This is predominantly the result of capital revenue being $2.42 million (7.2%), operating revenue being $3.25 million (1.0%) above forecast and total controllable operating expenditure being $4.77 million (6.7%) below forecast. Performance is continually monitored to ensure that controllable expenditure is minimised. This is achieved through rigorous internal processes which include the detailed review of all projects to ensure that only prudent and efficient expenditure is incurred. 16 RECOMMENDATION It is recommended that Council resolves as follows: That Council notes the Water and Sewerage Services Monthly Financial Report for the period ended 31 January 2021. Author: Authorised by: Karen O’Brien Paul Heaton Manager Business Performance Director Water and Waste 19 February 2021 OBJECTIVE REF: A63995103 COMMITTEE RECOMMENDATION WWE21.0303.004 moved Cr Tozer seconded Cr PJ Young That Council notes the Water and Sewerage Services Monthly Financial Report for the period ended 31 January 2021. CARRIED
799th Council Meeting 9 March 2021 39 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes Attachment 5.1 Financial Management Report – 31 January 2021 Water & Sewerage Services Year to Date Full Year Income Statement Act Revised Var Var Initial Revised Budget Budget Budget 31 January 2021 $000's $000's $000's % $000's $000's Revenue Access Charges 149,511 150,008 (498) (0.3%) 258,943 258,943 Usage Charges Revenue 161,063 157,540 3,524 2.2% 267,989 267,599 Less: Concealed Leakage (1,078) (1,231) 152 12.4% (2,500) (2,110) Interest on Outstanding Rates 421 391 30 7.8% 670 670 Interest on Investments 1,784 1,790 (6) (0.3%) 5,660 3,069 Fees and Charges 3,016 2,970 46 1.5% 5,389 4,979 Grants & Subsidies Revenue 90 90 - 0.0% 0 180 Total Operating Revenue 314,807 311,558 3,249 1.0% 536,150 533,329 Operating Expenditure FLOW-DEPENDENT EXPENDITURE Bulk Water Purchases 115,299 114,115 (1,184) (1.0%) 188,353 188,353 Electricity 6,222 7,300 1,078 14.8% 12,519 12,519 Biosolids Disposal 3,084 3,249 165 5.1% 5,673 5,673 Chemicals 2,201 2,483 283 11.4% 4,250 4,257 Total Flow -Dependent 126,806 127,148 342 0.3% 210,794 210,802 Expenditure Operating Revenue net of Flow - 188,001 184,411 3,591 1.9% 325,357 322,528 dependent Expenditure Gross Margin 0.6 0.6 0.6 0.6 CONTROLLABLE EXPENDITURE Employee Expenses 28,372 29,847 1,476 4.9% 49,045 51,340 Materials and Services 17,528 19,033 1,505 7.9% 37,320 34,766 Council Corporate SLAs 11,770 11,770 (0) (0.0%) 20,177 20,177 Internal Directorate SLA (3,179) (3,179) - 0.0% (5,450) (5,450) Fleet and Plant 5,542 5,074 (467) (9.2%) 8,755 8,782 Sew age Treatment Charge 1,784 2,333 550 23.6% 4,000 4,000 Insurance Premiums 1,103 1,103 - 0.0% 1,891 1,891 Other Expenditure 1,461 1,458 (3) (0.2%) 2,500 2,500 Consultants 1,781 3,472 1,690 48.7% 2,037 5,095 Regulatory Expenses 9 33 23 71.2% 143 143 Total Controllable Expenditure 66,171 70,945 4,774 6.7% 120,416 123,243 Total Operating Expenditure 192,977 198,092 5,115 2.6% 331,210 334,044 Loss on Sale of Assets 314 2,222 1,908 85.9% 5,000 5,000 Net Profit before Capital Revenue 121,516 111,244 10,272 9.2% 199,941 194,285 Capital Revenue Developers Contributions 27,333 20,417 6,916 33.9% 35,000 35,000 Contributions and Donations Received (0) 0 (0) 0.0% 0 0 Contributed Assets 8,837 13,333 (4,497) (33.7%) 30,000 30,000 Total Capital Revenue 36,169 33,750 2,419 7.2% 65,000 65,000 EBITDA 157,685 144,994 12,691 8.8% 264,941 259,285 Depreciation 59,063 57,633 (1,429) (2.5%) 98,800 98,800 EBIT 98,622 87,360 11,262 12.9% 166,141 160,485 Interest Expense (QTC Loan) 1,150 1,096 (54) (4.9%) 1,879 1,879 Interest Margin Expense 514 514 0 0.0% 881 881 Shareholder Interest Expense 51,814 51,814 - 0.0% 88,824 88,824 Income Tax Equivalents 23,087 19,096 (3,991) (20.9%) 32,682 32,682 NPAT 22,058 14,841 7,217 48.6% 41,875 36,219 Contribution - Whole of City 10,500 10,500 0 0.0% 18,000 18,000 projects Retained earnings im pact after 11,558 4,341 7,217 166.3% 23,875 18,219 participation return
799th Council Meeting 9 March 2021 40 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 6 WATER AND WASTE WASTE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/20(P6) Attachment 1: Detailed Income Statement 1 BASIS FOR CONFIDENTIALITY Not Applicable. 2 EXECUTIVE SUMMARY Not Applicable. 3 PURPOSE OF REPORT This report presents the Water, Waste and Energy Committee with Waste Services 2020-21 financial performance as at 31 January 2021. Comparisons are against Council’s 2020-21 September revised budget. 4 PREVIOUS RESOLUTIONS Not Applicable. 5 DISCUSSION 5.1 High Level Financial Summary Waste Services Financial Year to Date Full Year Revised Initial Revised Summary Actual Budget Var Var Budget Budget 31 January 2020 $M $M $M % $M $M Operating Revenue 65.57 66.93 (1.36) (2.0%) 111.37 114.16 Operating Expenses 44.93 47.07 2.14 4.6% 87.48 87.84 Total Operating Profit 20.64 19.86 0.78 4.0% 23.89 26.32 Loss on Sale of Assets 0.00 0.00 0.00 0.0% 0.00 0.00 EBITDA 20.64 19.86 0.78 4.0% 23.89 26.32 Table 1 - Waste Services - Year to Date Financial Summary Table 1 presents the financial position for Waste Services as at 31 January 2021 as $0.78 million (4.0%) above forecast. Variances will be discussed in the following paragraphs with a detailed Income Statement contained in Attachment 4.1 to the report. 5.2 Operating Revenue ($1.36 million Unfavourable) Operating revenue is $1.36 million behind forecast and is influenced by the following: § Waste Utility Revenue ($0.71 million Unfavourable): Representing just a little over 1% variance, this revenue stream is tracking very close to forecast. The variance is predominantly due to growth being slightly below forecast growth.
799th Council Meeting 9 March 2021 41 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 6 (Continued) WASTE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/20(P6) § Waste Levy Receipts ($0.33 million Unfavourable): The variance is due to a combination of the Waste Levy driving positive waste behaviour as well as the impact of COVID-19, resulting in a steady decline in volumes of commercial and industrial waste to landfill and subsequently waste levy receipts. The budget will be closely monitored and adjusted at the March budget review if required. § Gate Fees ($0.67 million Unfavourable): Gate fees are tracking below forecast as a result of commercial customers reducing their volumes of waste to landfill. This trend has been occurring since the introduction of the waste levy and has also been impacted by business closures due to COVID-19. Waste volumes will be closely monitored and will be adjusted at the March budget review if required. § Recycling Revenue ($0.25 million Favourable): This variance predominantly relates to three commodities: • Revenue from scrap steel sales – during the early stages of the COVID-19 pandemic scrap metal was stockpiled whilst contractors were not allowed on site. At the beginning of this financial year the stockpile was cleared resulting in this higher than normal revenue for the period. • Cardboard commodity rates have increased more than expected leading to a small revenue stream, where the likelihood for revenue was not initially forecast. • Container Refund Scheme was forecast to slowly decrease as residents take up the opportunity to exchange containers for change, however there was an unexpected increase in the first quarter of the year as more eligible containers were recovered through yellow top bins. Revenue will be closely monitored and will be adjusted at the March budget review if required. 5.2.1 Number of Waste Collection Bins in Service Table 2 presents the number of waste collection bins in service as at 31 January 2021. A customer may have multiple services of a bin on a weekly basis. Year to Date Waste collection bins Bins in service Bins in service Bin increase\ as at 31/1/2021 as at 30/06/2020 (decrease) % General w aste (w eekly) Domestic w heelie bins 196,568 195,581 987 0.5% Commercial w heelie bins 7,629 7,096 533 7.5% Bulk bins (domestic and commercial) 3,132 3,106 26 0.8% Total w eekly general w aste services 207,329 205,783 1,546 0.8% Recyclable w aste (w eekly) Commercial w heelie bins 433 401 32 8.0% Bulk bins (domestic and commercial) 1,729 1,701 28 1.6% Total w eekly recyclable w aste services 2,162 2,102 60 2.9% Recyclable w aste (fortnightly) Domestic w heelie bins 188,901 187,775 1,126 0.6% Commercial w heelie bins 3,171 2,705 466 17.2% Total fortnightly recyclable w aste services 192,072 190,480 1,592 0.8% Other (fortnightly) Green w aste 42,384 39,722 2,662 6.7% Total fortnightly other services 42,384 39,722 2,662 6.7% Food w aste (w eekly) Bulk bins (domestic and commercial) 40 40 0 0.0% Table 2 - Waste Collection Bins in Service
799th Council Meeting 9 March 2021 42 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 6 (Continued) WASTE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/20(P6) As part of the Utility Billing System Stabilisation Program, a waste data integrity review is being undertaken. This review will ensure that services are correctly allocated as Residential or Commercial, along with the associated waste levy application. As a result, domestic bins will show only small growth percentages in some months, whilst commercial services will show more positive growth numbers which is also coupled with a bounce back from reduced services during COVID-19 shutdowns. 5.3 Operating Expenditure ($2.14 million Favourable) At a whole business unit level, operating expenses are $2.14 million (4.6%) below forecast. The major contributors to this variance are discussed below. § Materials and Services ($1.26 million Favourable): The main reason for this variance is due to the following: • Materials Recycling Facility (MRF) - Recycling volumes from yellow top bins processed by the Visy MRF have dropped by 8% YTD on forecast. The Container Refund Scheme has contributed to a decrease in processing costs. • Wheelie Bin Acquisitions - Wheelie bin purchases have been lower than forecast due to lower than forecast growth. In addition, bins for the commercial food waste trial are below forecast due to the reduced uptake of the program due to COVID-19. • Concrete Crushing – A new contract was awarded in June 2020 and services resumed in August. Expenditure is expected to meet budget by year end. • Commercial Food Waste - Collection and processing costs are lower than forecast due to a slower than anticipated bounce back to normal services after COVID-19 shutdowns. The budget is being closely monitored and will be adjusted at the March budget review if required. § Waste Collection Payments ($0.84 million Favourable): The majority of this variance relates to the bulky kerbside collection service. The ‘on-demand’ service was extended city wide in January 2021. It is anticipated that as the service is promoted and becomes more visible, customer uptake will increase. In addition, general waste collections are slightly below forecast due to lower than forecast growth. § Fleet and Plant ($0.38 million Favourable): External Fleet and Plant hire at the Coomera Waste and Recycling Centre has reduced from initial site set up. Appropriate adjustments will be proposed as part of the March budget review. § Waste Levy Payments ($0.33 million Unfavourable): Waste Levy Payment to the State Government is higher than forecast by 3.92%. An increase in waste volumes from other Directorates of Council has resulted in the increase.
799th Council Meeting 9 March 2021 43 Water, Waste and Energy Committee Meeting 3 March 2021 Adopted Minutes ITEM 6 (Continued) WASTE SERVICES FINANCIAL PERFORMANCE AS AT 31 JANUARY 2021 FN334/252/20(P6) § Consultants ($0.18 million Unfavourable): Annual and monthly pump monitoring at Stapylton landfill is being undertaken by a specialist consultant. The budget for this body of work was omitted from the initial budget and will be requested as part of the upcoming March budget review. The overall consultancy budget was reduced at the September budget review due to the planned Waste Data Integrity Review being merged and delivered with the Utility Billing System Stabilisation project. 5.4 Capital Program The revised 2020-21 Waste Services capital program consists of sixteen projects totalling $8.70 million. Waste Services Capital Expenditure as at 31 January 2021 Product Year to Date Full Year Initial Actual Revised Budget Variance Variance Revised Budget Budget Expenditure ($M) ($M) ($M) % ($M) ($M) Landfills 2.50 3.18 (0.68) (21%) 3.95 2.85 Waste and Recycling Centres 0.90 3.53 (2.63) (74%) 4.75 2.88 Total Capital 3.40 6.71 (3.31) (49%) 8.70 5.73 Table 3 – Capital Expenditure ($ Million) Year to date capital expenditure of $3.40 million represents a variance of 49%, or $3.31 million below the year to date revised forecast of $6.71 million. The following projects are the main contributors to this variance: Product Variances Landfills The landfill program is $0.68 million (21%) below forecast. The following project is the main contributor to this variance: • Stapylton Landfill Main Access Upgrade: $0.73 million below forecast. Project impacted by design delays due to site and operational requirements. Despite the construction delay, it is anticipated there will be a request for additional funding as part of the March budget review 2021 budget review to allow for the required modifications. The project is still on track for completion by 30 June 2021.
You can also read